Page 11 - 3GPP_Highlights_Issue_5_WEB
P. 11
Study items based on continuation of Rel-17 work
• Study on 5GC enhancement for satellite access Phase 2 • Study on Access Traffic Steering, Switching and Splitting
(FS_5GSAT_Ph2, TR 23.700-28) support in the 5G system architecture; Phase 3
(FS_ATSSS_Ph3, TR 23.700-53)
• Study on Phase 2 of UAS, UAV and UAM
(FS_UAS_Ph2, TR 23.700-58) • Study on Stage 2 of Edge Computing Phase 2
(FS_EDGE_Ph2, TR 23.700-48)
• Study on Enhancement to the 5GC LoCation Services-Phase 3
(FS_eLCS_Ph3, TR 23.700-71) • Study on enhancement of support for 5WWC
(FS_5WWC_Ph2, TR 23.700-17)
• Study on Stage 2 for Proximity based Services Phase 2
(FS_5G_ProSe_Ph2, TR 23.700-33) • Study on Enablers for Network Automation for 5G - phase 3
(FS_eNA_Ph3, TR 23.700-81)
• Study on architectural enhancements for 5G multicast-
broadcast services Phase 2 • Study on enhanced support of Non-Public Networks phase 2
(FS_5MBS_Ph2, TR 23.700-47) (FS_eNPN_Ph2, TR 23.700-08)
• Study on Enhancement of Network Slicing Phase 3 • Work Item on Stage 2 of MPS when access to EPC/5GC is WLAN
(FS_eNS_Ph3, TR 23.700-41) (MPS_WLAN)
• Study on RedCap Phase 2
(FS_REDCAP_Ph2, TR 23.700-68)
Despite the e-meeting challenges, SA2 continues to make good progress on Rel-18 work, thanks to the
meticulous SA2 work planning, technical document budget allocation per Time Unit (TU), and outstanding
effort of the meeting participants. At the time of writing, Rel-18 Study items are between 70% - 100% complete.
SA2 plans to finish the Stage-2 normative work by Mar 2023. Rel-18 Stage-3 target freeze date is Dec 2023 and
ASN.1/Code freeze target is Mar 2024.
2021 2022 2023 2024
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TSG#94-e TSG#95-e TSG#96 TSG#97 TSG#98 TSG#99 TSG#100 TSG#101 TSG#102 TSG#103 TSG#103
Dec. Mar. Jun. Sep. Dec. Mar. Jun. Sep. Dec. Mar. Mar.
Rel-17 Rel-17
Protocol
Stage 3 Coding
Freeze Freeze
(ASN.1, OPENAPI)
Rel-18 Rel-18 Rel-18 Rel-18
Package Stage 2 Stage 3 Protocol
(content) Functional Coding
Freeze
Approval Freeze Freeze (ASN.1, OPENAPI)
Rel-19
Rel-19 Stage1, Study Phase
TM Package
(content)
Approval*
*date TBD
|
Issue 05 - No v ember 2 0 22 11