Tdoc List
2025-04-02 11:21
Agenda | Topic | TDoc | Title | Source | Type | For | Avail | Treated | Decision | Wdrn | Replaced-by | Replaces |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Opening of the meeting | |||||||||||
2 | Approval of the agenda | S5‑251200 | Agenda | WG Chair | agenda | Yes |
No
| available | No | |||
3 | IPR and legal declaration | S5‑251201 | IPR and legal declaration | WG Chair | other | Yes |
No
| available | No | |||
4 | Meetings and activities reports | |||||||||||
4.1 | Last SA5 meeting report | S5‑251202 | Report from last SA5 meeting | MCC | report | Yes |
No
| available | No | |||
4.2 | Inter-organizational reports | |||||||||||
5 | SA5 level issues | |||||||||||
5.1 | Administrative issues at SA5 level | S5‑251203 | Time Plan for SA5 Plenary and OAM sessions | WG Chair | agenda | No |
No
| reserved | No | |||
S5‑251204 | agenda_with_Tdocs_sequence_Plenary&OAM | WG Chair | agenda | No |
No
| reserved | No | |||||
S5‑251205 | SA5 working procedures | WG Chair | other | Yes |
No
| available | No | |||||
S5‑251206 | SA5 Meeting facility requirements | WG Chair | other | Yes |
No
| available | No | |||||
S5‑251208 | Post meeting email approval status | WG Vice Chair (Ericsson) | other | No |
No
| reserved | No | |||||
S5‑251211 | Plenary and OAM Chair notes and conclusions | WG Chair | report | No |
No
| reserved | No | |||||
S5‑251214 | Rel-19 SA5 work plan TU table | WG Chair | other | Yes |
No
| available | No | |||||
S5‑251218 | Latest SA5 Rel-19 WIs-SIs | WG Chair | other | Yes |
No
| available | No | |||||
S5‑251219 | Rel-19 SA5 work planning | WG Chair | other | Yes |
No
| available | No | |||||
S5‑251220 | Rel-20 SA5 work planning | WG Chair | other | Yes |
No
| available | No | |||||
S5‑251413 | Maintenance of TSs in SA5 | Ericsson | discussion | Endorsement | Yes |
No
| available | No | ||||
S5‑251758 | Selecting the Release for the SA5 OAM and Charging aspects | SA5 leadership & MCC | other | Agreement | Yes |
No
| available | No | ||||
5.2 | Technical issues at SA5 level | |||||||||||
5.3 | Liaison statements at SA5 level | S5‑251328 | LS on Ambient IoT progress of RAN3 | RAN3 | LS in | Information | Yes |
No
| available | No | ||
S5‑251330 | Publication of ETSI NFV group report on architectural support for NFV evolution | ETSI ISG NFV | LS in | Information | Yes |
No
| available | No | ||||
S5‑251409 | Reply LS on per-UE UE performance metrics | NEC, Intel | LS out | Approval | Yes |
No
| available | No | ||||
5.4 | SA5 meeting calendar | S5‑251207 | SA5 meeting calendar | WG Chair | other | Yes |
No
| available | No | |||
5.5 | Rel-20 topic preparation | S5‑251366 | New WID on OAM for XR and media services (XRM) | ZTE Corporation | WID new | Agreement | Yes |
No
| available | No | ||
S5‑251387 | New SID on energy efficiency and energy saving aspects of 5G Advanced | Huawei | SID new | Agreement | Yes |
No
| available | No | ||||
S5‑251453 | SA5 Rel-20 5GA 25Q1 moderated discussion – ISAC management | ZTE Corporation | other | Approval | Yes |
No
| available | No | ||||
S5‑251489 | New SID on SBMA enhancement phase 4 | Moderator (Huawei) | SID new | Agreement | Yes |
No
| available | No | ||||
S5‑251498 | New SID on Management aspect of Network Digital Twins phase 2 | China Mobile | SID new | Approval | Yes |
No
| available | No | ||||
S5‑251558 | New SID Study on intent driven management services for mobile network phase 4 | Moderator (Huawei, Ericsson) | SID new | Agreement | Yes |
No
| available | No | ||||
S5‑251593 | WID on Study on Management Data Analytics (MDA) – Phase 4 | Huawei Tech. Japan, K.K. | SID new | Approval | Yes |
No
| available | No | ||||
S5‑251634 | New SID on cloud aspects of management and orchestration phase 2 | China Mobile | SID new | Approval | Yes |
No
| available | No | ||||
S5‑251652 | New SID on Semantic-based Network Management | Moderator(China Unicom, Samsung) | SID new | Approval | Yes |
No
| available | No | ||||
S5‑251740 | New SID on Study for Data management phase 3 | Nokia | SID new | Approval | Yes |
No
| available | No | ||||
6 | OAM&P | |||||||||||
6.1 | OAM&P Plenary | S5‑251209 | OAM action list | WG Vice Chair (Nokia) | other | No |
No
| reserved | No | |||
S5‑251210 | OAM Exec Report | WG Vice Chair (Nokia) | report | No |
No
| reserved | No | |||||
S5‑251212 | Collection of useful endorsed documents in OAM | WG Vice Chair (Nokia) | discussion | No |
No
| reserved | No | |||||
S5‑251213 | Collection of external communication documents in OAM | WG Vice Chair (Nokia) | discussion | No |
No
| reserved | No | |||||
S5‑251221 | OAM breakout notes | WG Chair | report | No |
No
| reserved | No | |||||
S5‑251222 | Support Continuous MDT on reply to RAN3 incoming LS (R3-250788) | Ericsson, AT&T, CMCC | discussion | Endorsement | Yes |
No
| available | No | ||||
S5‑251223 | Reply LS to LS on Continuous MDT | Ericsson LM | LS out | Approval | Yes |
No
| available | No | ||||
S5‑251226 | LS on the new NGMN Publication: ‘MLOps for Highly Autonomous Network’ | NGMN Alliance | LS in | Information | Yes |
No
| available | No | ||||
S5‑251314 | Reply LS to ITU-T SG2 on methodology coordination | WG vice chair (Ericsson) | LS out | Approval | Yes |
No
| available | No | ||||
S5‑251322 | LS on 5G Trace to support UE level measurement (SA5#159) | CT4 | LS in | Information | Yes |
No
| available | No | ||||
S5‑251323 | LS reply to LS on energy information collection from OAM to EIF | CT | LS in | Information | Yes |
No
| available | No | ||||
S5‑251324 | LS on per-UE UE performance metrics (SA5#159) | RAN3 | LS in | Information | Yes |
No
| available | No | ||||
S5‑251325 | Reply LS on MBS Communication Service Type | RAN3 | LS in | Information | Yes |
No
| available | No | ||||
S5‑251326 | LS on Continuous MDT | RAN3 | LS in | Information | Yes |
No
| available | No | ||||
S5‑251327 | Reply LS on OAM requirements to support regenerative payload transport links | RAN3 | LS in | Information | Yes |
No
| available | No | ||||
S5‑251331 | LS on the initiation of a new Technical Report ITU-T TR.M.rnscesnr “Requirements of network service consistency evaluation for shared network resources” | ITU-T SG2 | LS in | Information | Yes |
No
| available | No | ||||
S5‑251332 | LS/r on methodology harmonization update (reply to 3GPP TSG SA5-244109 - LS57) | ITU-T SG2 | LS in | Information | Yes |
No
| available | No | ||||
S5‑251372 | LS on the consent of Recommendation ITU-T M. 3042(ex. M.fcnhe): "Framework of communication network health evaluation" | ITU-T SG2 | LS in | Information | Yes |
No
| available | No | ||||
S5‑251615 | LS reply to LS on 5G Trace to support UE level measurement | Huawei | LS out | Approval | Yes |
No
| available | No | ||||
S5‑251741 | Continuous MDT Discussion | Nokia | discussion | Endorsement | Yes |
No
| available | No | ||||
S5‑251742 | Reply LS on Continuous MDT | Nokia | LS out | Approval | Yes |
No
| available | No | ||||
6.2 | New OAM&P Work Item proposals | |||||||||||
6.2.1 | Intelligence and Automation | S5‑251316 | New Study on AI/ML management enhancements | NEC, Intel | SID new | Agreement | Yes |
No
| available | No | ||
6.2.2 | Management Architecture and Mechanisms | S5‑251230 | Revised WID on 5G performance measurements and KPIs phase 4 | Ericsson LM | WID revised | Agreement | Yes |
No
| available | No | ||
S5‑251627 | Rel-19 Revised WID on Management Aspects of NTN Phase 2 | CATT, China Unicom | WID revised | Approval | Yes |
No
| available | No | ||||
6.2.3 | Support of New Services | S5‑251529 | Revised WID on Management Aspects of NTN Phase 2 | Samsung R&D Institute UK | WID revised | Yes |
No
| available | No | |||
6.3 | Pre-Rel-18 Maintenance | |||||||||||
6.3.1 | Methodology | |||||||||||
6.3.2 | ANL | |||||||||||
6.3.3 | MDAS | |||||||||||
6.3.4 | AI/ML | |||||||||||
6.3.5 | Energy efficiency | S5‑251664 | Rel-17 CR TS 28.310 Clarify information of service | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||
S5‑251665 | Rel-18 CR TS 28.310 Clarify information of service | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251666 | Rel-19 CR TS 28.310 Clarify information of service | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
6.3.6 | Intent driven management | |||||||||||
6.3.7 | SON | S5‑251429 | Rel-16 CR 28.541 Update for allowed value ueAccProbabilityDist (stage3, yang) | Ericsson Canada Inc. | CR | Agreement | Yes |
No
| available | No | ||
S5‑251430 | Rel-17 CR 28.541 Update for allowed value ueAccProbabilityDist (stage3, yang) | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251431 | Rel-18 CR 28.541 Update for allowed value ueAccProbabilityDist (stage3, yang) | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251432 | Rel-19 CR 28.541 Update for allowed value ueAccProbabilityDist (stage3, yang) | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
6.3.8 | QMC | |||||||||||
6.3.9 | Network slicing management | S5‑251667 | Rel-16 CR TS 28.530 Clarify tenant information concept | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||
S5‑251668 | Rel-17 CR TS 28.530 Clarify tenant information concept | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251669 | Rel-18 CR TS 28.530 Clarify tenant information concept | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251670 | Rel-19 CR TS 28.530 Clarify tenant information concept | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
6.3.10 | MEC management | |||||||||||
6.3.11 | General NRM | S5‑251295 | Rel19 CR TS28.541 correction to inconsistency between stage 2 and stage 3 concerning SubNetwork and ManagedElement containment | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||
S5‑251296 | Rel18 CR TS28.541 correction to inconsistency between stage 2 and stage 3 concerning SubNetwork and ManagedElement containment | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251297 | Rel18 CR TS28.541 correction to stage 3 of SatelliteBackhaulInfo | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251298 | Rel19 CR TS28.541 correction to stage 3 of SatelliteBackhaulInfo | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251418 | Rel-17 CR 28.622 Change dnPrefix properties | Ericsson India Private Limited | CR | Approval | No |
Yes
| withdrawn | Yes | ||||
S5‑251419 | Rel-17 CR 28.622 Change dnPrefix properties | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251420 | Rel-18 CR 28.622 Change dnPrefix properties | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251421 | Rel-19 CR 28.622 Change dnPrefix properties | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251424 | Rel-17 CR 28.623 Change dnPrefix properties | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251425 | Rel-18 CR 28.623 Change dnPrefix properties | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251426 | Rel-19 CR 28.623 Change dnPrefix properties | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251595 | Rel-17 CR TS 28.541 Fix invalid reference | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251703 | Rel15 CR TS 32.156 Enhancement of the description of the “isNotifyable” attribute property | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251704 | Rel16 CR TS 32.156 Enhancement of the description of the “isNotifyable” attribute property and correction of the default value for the “isReadable” attribute property | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251705 | Rel17 CR TS 32.156 Enhancement of the description of the “isNotifyable” attribute property and correction of the default value for the “isReadable” attribute property | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251706 | Rel18 CR TS 32.156 Enhancement of the description of the “isNotifyable” attribute property and correction of the default value for the “isReadable” attribute property | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251707 | Rel19 CR TS 32.156 Enhancement of the description of the “isNotifyable” attribute property and correction of the default value for the “isReadable” attribute property | Nokia | CR | Approval | Yes |
No
| available | No | ||||
6.3.12 | PM/KPI | |||||||||||
6.3.13 | Trace/MDT | |||||||||||
6.3.14 | Other | S5‑251349 | Rel19 CR TS28.104 correction to reference | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||
S5‑251591 | Rel-18 CR 28541 Correct support qualifier condition for ephemerisInfoSetRef | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
6.4 | Rel-18 Maintenance and Rel-19 small Enhancements | |||||||||||
6.4.1 | Self-Configuration of RAN NEs | S5‑251673 | Rel-18 CR TS 28.317 Correct import table | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||
S5‑251674 | Rel-19 CR TS 28.317 Correct import table | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
6.4.2 | Management Data Analytics phase 2 | S5‑251624 | Rel 18 CR TS 28.104 Correct References for MDA reporting | Ericsson | CR | Approval | Yes |
No
| available | No | ||
S5‑251625 | Rel 19 CR TS 28.104 Correct References for MDA reporting | Ericsson | CR | Approval | Yes |
No
| available | No | ||||
6.4.3 | AI/ML management | S5‑251352 | Rel-18 CR TS 28.105 Correction on the isWritable propoerty of AIMLInferenceName in the MLTrainingRequest | ZTE Corporation, Intel, Huawei | CR | Agreement | Yes |
No
| available | No | ||
S5‑251353 | Rel-19 CR TS 28.105 Correction on the isWritable propoerty of AIMLInferenceName in the MLTrainingRequest | ZTE Corporation, Intel, Huawei | CR | Agreement | Yes |
No
| available | No | ||||
6.4.4 | Intent driven Management Service for mobile network phase 2 | S5‑251671 | Rel-18 CR TS 28.312 Correct import table | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||
S5‑251672 | Rel-19 CR TS 28.312 Correct import table | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
6.4.5 | Service based management architecture | S5‑251416 | Rel-18 CR 28.111 How to use notifyPotentialFaultyAlarmList | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||
S5‑251417 | Rel-19 CR 28.111 How to use notifyPotentialFaultyAlarmList | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251438 | Rel-19 CR 28.622 Remove deprecated notification | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251439 | Rel-19 CR 28.541 Remove deprecated notification | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251451 | Rel-18 CR 28.623 Modify YANG mapping of Subnetwork | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251452 | Rel-19 CR 28.623 Modify YANG mapping of Subnetwork | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251459 | Rel-18 CR 28.541 Modify YANG mapping of Subnetwork | Ericsson India Private Limited | CR | Approval | No |
Yes
| withdrawn | Yes | ||||
S5‑251461 | Rel-19 CR 28.541 Modify YANG mapping of Subnetwork | Ericsson India Private Limited | CR | Approval | No |
Yes
| withdrawn | Yes | ||||
S5‑251479 | Rel-18 CR TS 28.111 Add missing solution components | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251480 | Rel-19 CR TS 28.111 Add missing solution components | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251481 | Rel-18 CR TS 28.111 Correction on reliability of alarm lists | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251482 | Rel-19 CR TS 28.111 Correction on reliability of alarm lists | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251543 | Rel 18 CR TS 28.532 correct the format of scope parameter to align with stage3 | HUAWEI | CR | Approval | Yes |
No
| available | No | ||||
S5‑251544 | Rel 19 CR TS 28.532 correct the scope operation parameter in stage 3 | Huawei | CR | Approval | Yes |
No
| available | No | ||||
S5‑251562 | Rel-18 CR TS 28.111 Clarify notifyChangedAlarmGeneral | Huawei, Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251563 | Rel-19 CR TS 28.111 Clarify notifyChangedAlarmGeneral | Huawei, Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251564 | Rel-18 CR TS 28.111 Add missing ThresholdInfo dataType and related definition | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251565 | Rel-19 CR TS 28.111 Add missing ThresholdInfo dataType and related definition | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251730 | Rel-19 CR 28.622 Add new generic type KeyValueList | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
6.4.6 | Network slicing provisioning rules | |||||||||||
6.4.7 | Network slice provisioning enhancement | |||||||||||
6.4.8 | Management of Trace/MDT phase 2 | S5‑251616 | Rel-18 CR 32.422 Clarification on SMF obtaining Trace control and measurement parameters from UDM | Huawei | CR | Agreement | Yes |
No
| available | No | ||
S5‑251617 | Rel-18 CR 32.422 Clarification on SMF obtaining trace control and configuration parameters from UDM | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
6.4.9 | 5G performance measurements and KPIs phase 3 | S5‑251234 | Rel-18 CR TS 28.552 Corrections of subcounters and filters | Ericsson, Rakuten Mobile, Samsung | CR | Agreement | Yes |
No
| available | No | ||
S5‑251235 | Rel-19 CR TS 28.552 Corrections of subcounters and filters | Ericsson, Rakuten Mobile, Samsung | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251236 | Rel-18 CR TS 28.552 Distribution of UE throughput | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251237 | Rel-19 CR TS 28.552 Distribution of UE throughput | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251587 | Rel-19 CR 28.532 Enhance notifyFilePreparationError definition | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251597 | Rel-18 CR TS 28.552 PLMN name inconsistency | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251598 | Rel-19 CR TS 28.552 PLMN name inconsistency | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251692 | Rel-18 CR TS28.552 Add missing EP_N9 for GTP capacity related measurements | ZTE Corporation | CR | Approval | Yes |
No
| available | No | ||||
S5‑251693 | Rel-19 CR TS28.552 Add missing EP_N9 for GTP capacity related measurements | ZTE Corporation | CR | Approval | Yes |
No
| available | No | ||||
S5‑251737 | Rel-19 CR TS 28.558 Correction on the UE identifer | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251738 | Rel-19 CR TS 28.552 Corrections on Filter Definition | Nokia | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251739 | Rel-19 CR TS 28.552 Corrections on Filter Definition | Nokia | CR | Approval | Yes |
No
| available | No | ||||
6.4.10 | Enhancement of QoE Measurement Collection | |||||||||||
6.4.11 | Additional NRM features phase 2 | S5‑251350 | Rel-18 CR TS 28.541 Typo corrections and missing definitions | ZTE Corporation, Orange | CR | Agreement | Yes |
No
| available | No | ||
S5‑251351 | Rel-19 CR TS 28.541 Typo corrections and missing definitions | ZTE Corporation, Orange | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251659 | Rel-19 CR 28.541 Align predefinedPccRuleSet attributes with the definitions in TS 29.512 | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251689 | Rel-19 CR TS28.541 Fix isOrdered and isUnique Attribute properties | ZTE Corporation | CR | Approval | Yes |
No
| available | No | ||||
6.4.12 | Management Aspects related to NWDAF | |||||||||||
6.4.13 | Enhanced Edge Computing Management | |||||||||||
6.4.14 | Management Aspect of 5GLAN | |||||||||||
6.4.15 | Management Aspects of NTN | S5‑251690 | Rel-18 CR TS28.541 Fix nTNTAClist for stage 3 OpenAPI | ZTE Corporation | CR | Approval | Yes |
No
| available | No | ||
S5‑251691 | Rel-19 CR TS28.541 Fix nTNTAClist for stage 3 OpenAPI | ZTE Corporation | CR | Approval | Yes |
No
| available | No | ||||
6.4.16 | methodology for deprecation | |||||||||||
6.4.17 | Management of cloud-native Virtualized Network Functions | |||||||||||
6.4.18 | Management Aspects of 5G Network Sharing Phase2 | |||||||||||
6.4.19 | Management Aspects of URLLC | |||||||||||
6.4.20 | Management aspects of 5G system supporting satellite backhaul | |||||||||||
6.4.21 | Access control for management service | |||||||||||
6.4.22 | Enhancements of EE for 5G Phase 2 | |||||||||||
6.4.23 | Management of non-public networks phase 2 | S5‑251561 | Rel-18 CR TS 28.557 Update procedure of management of tenant to align with access control solution | Huawei | CR | Agreement | Yes |
No
| available | No | ||
S5‑251729 | Rel-18 CR TS 28.557 Fix wrong references and correct solution for NPN-SC mgmt | Ericsson GmbH, Eurolab | CR | Agreement | Yes |
No
| available | No | ||||
6.4.24 | Network and Service Operations for Energy Utilities | S5‑251716 | Rel-18 CR TS 28.318 Fix affectedArea attribute for DSO service outage use case | Ericsson GmbH, Eurolab | CR | Agreement | Yes |
No
| available | No | ||
S5‑251717 | Rel-19 CR TS 28.318 Fix affectedArea attribute for DSO service outage use case | Ericsson GmbH, Eurolab | CR | Yes |
No
| available | No | |||||
6.4.25 | Rel-18 CAT B/C alignment CR(s) due to the work led by other 3GPP Working Groups | |||||||||||
6.4.26 | Rel-18 CAT B/C SA5 internal alignment and other CAT F CR(s) | S5‑251233 | Rel-18 CR TS 32.404 Corrections on measurement name size | Ericsson | CR | Agreement | Yes |
No
| available | No | ||
S5‑251282 | Rel-18 CR 28.111 YANG stage-3 corrections | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251283 | Rel-19 CR 28.111 YANG stage-3 corrections | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251284 | Rel-18 CR 28.623 YANG stage-3 corrections | Ericsson India Private Limited | CR | Approval | No |
Yes
| withdrawn | Yes | ||||
S5‑251285 | Rel-19 CR 28.623 YANG stage-3 corrections | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251286 | Rel-18 CR 28.623 YANG stage-3 corrections | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251289 | Rel-18 CR 28.541 YANG stage-3 corrections | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251290 | Rel-19 CR 28.541 YANG stage-3 corrections | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251406 | Rel-18 CR TS 28.111 Correction on Alarm Definition | NTT DOCOMO, Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251407 | Rel-19 CR TS 28.111 Correction on Alarm Definition | NTT DOCOMO, Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
6.4.27 | OAM Rel-19 small enhancements | S5‑251239 | Rel-19 CR TS 28.560 Corrections on networkInterfaceTypeList | Ericsson, Vodafone | CR | Agreement | Yes |
No
| available | No | ||
S5‑251240 | Rel-19 CR TS 28.560 Corrections on PCAPNG header | Ericsson, Vodafone | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251287 | Addressing ENs in TS 28.560 | Vodafone, Ericsson | CR | Approval | Yes |
No
| available | No | ||||
S5‑251288 | Removal of already addressed Editor's Note | Vodafone | CR | Approval | Yes |
No
| available | No | ||||
S5‑251380 | Rel-19 CR TS 28.622 Correct misalignment issue for notificationTypes in stage2 and stage3 | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251382 | Rel-19 CR TS 28.623 Update the YANG definition for notificationTypes to align with stage 2 definition | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251383 | Rel-19 CR TS 28.533 Correct wrong references | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251384 | Rel-19 CR TS 28.533 Fix errors in clause 4.5 | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251385 | Rel-19 CR TS 28.533 Correct note in clause 3.1 | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251389 | Rel-19 CR TS 28.623 Implement the writeOnly property for triggerHeartbeatNtf | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251390 | Rel-19 CR TS 28.622 Update Attribute constraints for TimeWindow | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251391 | Rel-19 CR TS 28.537 Correct procedures for heartbeat | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251414 | Addressing EN for supporting type of signalling | Vodafone, Samsung | CR | Approval | Yes |
No
| available | No | ||||
S5‑251415 | Removal of Editor's Note on encoding | Vodafone | CR | Approval | Yes |
No
| available | No | ||||
S5‑251500 | Rel-19 CR TS 28.622 Corrections of Trace Reference Notifications | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251557 | Rel-19 CR 28.541 Add control attribute for LTM cell switch | Ericsson | CR | Approval | Yes |
No
| available | No | ||||
S5‑251621 | Rel 19 CR TS 28.541 Remove support qualifier from attribute constraints for NR NRM | Ericsson | CR | Approval | Yes |
No
| available | No | ||||
S5‑251622 | Rel 19 CR TS 28.541 Remove support qualifier from attribute constraints for Network Slice NRM | Ericsson | CR | Approval | Yes |
No
| available | No | ||||
S5‑251623 | Rel 19 CR TS 28.541 Remove support qualifier from attribute constraints for 5GC NRM | Ericsson | CR | Approval | Yes |
No
| available | No | ||||
S5‑251628 | Rel-19 CR TS 28.541 Correction on wrong attribute property definition.docx | CATT | CR | Approval | Yes |
No
| available | No | S5‑250932 | |||
S5‑251649 | Correct the description of maximum number of PDU sessions of network slice | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251726 | Rel-19 CR TS 28.622 Correction of Area Scope Parameter | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251727 | Rel-19 CR TS 32.422 Correction of Area Scope Parameter | Nokia | CR | Approval | Yes |
No
| available | No | ||||
6.19 | OAM&P Rel-19 Study and Work Items | |||||||||||
6.19.1 | Study on AI/ML management - phase 2 (completed) | |||||||||||
6.19.1.1 | AI/ML management phase 2 | S5‑251258 | Input to draftCR TS28.105 Coordination AIML inference | Nokia | draftCR | Approval | Yes |
No
| available | No | ||
S5‑251259 | Input to draftCR TS28.105 Enhance AIML inference emulation | Nokia | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251260 | Input to draftCR TS28.105 NRM for AIML emulation environment | Nokia | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251261 | Input to draftCR TS28.105 NRM for ML-Knowledge-based TL | Nokia | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251354 | Input to DraftCR Rel-19 TS 28.105 Add Management Scenario for RL | ZTE Corporation, NEC, Intel | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251355 | Input to DraftCR Rel-19 TS 28.105 Add Procedure Diagram for FL Server selection and determination | ZTE Corporation,NEC, Intel | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251356 | Input to DraftCR Rel-19 TS 28.105 Add Procedure Diagram for FL Client selection | ZTE Corporation,NEC, Intel | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251357 | Input to DraftCR Rel-19 TS 28.105 Update the UC and Req of Reinforcement Learning | ZTE Corporation | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251358 | Input to DraftCR Rel-19 TS 28.105 Add New Use Case and Requirements of Sustainable AIML for ML training | ZTE Corporation | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251359 | Input to DraftCR Rel-19 TS 28.105 Add Solution for Sustainable AIML for ML training | ZTE Corporation | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251360 | Input to DraftCR Rel-19 TS 28.105 Enhancement on AIMLSupportedFunction to support inference in LMF | ZTE Corporation | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251361 | Rel-19 CR TS 28.541 Enhancement on LMF NRM to Support the Inference Functionality in LMF | ZTE Corporation | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251362 | Input to DraftCR Rel-19 TS 28.105 Add New AI/ML functionalities management scenario for LMF | ZTE Corporation | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251363 | Input to DraftCR Rel-19 TS 28.105 Add Solution for Distributed Learning | ZTE Corporation | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251364 | DP on the NRM Design for AIMLInferenceFunction | ZTE Corporation | discussion | Approval | Yes |
No
| available | No | ||||
S5‑251365 | Input to DraftCR Rel-19 CR TS 28.105 Enhancement on AIMLInferenceFunction NRM | ZTE Corporation | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251410 | Input to draftCR TS 28.105 Add NRMs on LCM for Federated Learning | Intel, NEC, ZTE, Samsung, Nokia | other | Approval | Yes |
No
| available | No | ||||
S5‑251411 | Input to draftCR TS 28.105 Add NRMs on LCM for Reinforcement Learning | Intel, ZTE, NEC | other | Approval | Yes |
No
| available | No | ||||
S5‑251412 | Input to draftCR TS 28.105 Enhance UC for management of Reinforcement Learning | Intel, NEC | other | Approval | Yes |
No
| available | No | ||||
S5‑251444 | Rel19 input to DraftCR TS28.105 New use case on Coordination between the ML capabilities | Nokia, Nokia Shanghai Bell, China mobile, TELUS | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251496 | Input to DraftCR Rel-19 TS 28.105 Add UC for prediction latency | China Mobile | other | Approval | Yes |
No
| available | No | ||||
S5‑251497 | Input to DraftCR Rel-19 TS 28.105 Add UC for AIML explainability | China Mobile | other | Approval | Yes |
No
| available | No | ||||
S5‑251506 | Input to draftCR TS 28.105 Pre-specialized training and Fine-tuning | China Mobile, ZTE | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251507 | Input to Draft CR Rel-19 CR TS 28.105 Add solution for Pre-specialized training and fine-tuning | China Mobile, ZTE | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251530 | Rel-19 InputToDraftCR 28.105 solution for Impact management | Samsung R&D Institute UK | draftCR | Yes |
No
| available | No | |||||
S5‑251541 | Rel-19 InputToDraftCR 28.105 RL UC and Requirements | Samsung R&D Institute UK | draftCR | Agreement | Yes |
No
| available | No | ||||
S5‑251545 | Rel-19 InputToDraftCR TS 28.105 enhance the description for managing AIML based capabilities | Huawei | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251546 | Rel-19 InputToDraftCR TS 28.105 add procedure of management of AIML capabilities for NG-RAN and MDA | Huawei | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251547 | Rel-19 InputToDraftCR TS 28.105 Update the description for managing ML models in use in a live network | Huawei | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251548 | Rel-19 InputToDraftCR TS 28.105 add solution for exploration in reinforcement learning | Huawei | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251549 | Rel-19 InputToDraftCR TS 28.105 Add use case and requirements for reinforcement learning conflict management | Huawei | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251550 | Rel-19 InputToDraftCR TS 28.105 Add solutions of training conflict management for reinforcement learning | Huawei | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251551 | Rel-19 InputToDraftCR TS 28.105 add use case for Management of Local explanation in AIML inference | Huawei | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251552 | Rel-19 InputToDraftCR TS 28.105 add solution for Management of Local explanation in AIML inference | Huawei | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251553 | Rel-19 InputToDraftCR TS 28.105 update the ML model lifecycle management capabilities | Huawei | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251606 | Input to draftCR Rel-19 TS 28.105 Use case on AIML prediction latency in inference | Nokia, Nokia Shanghai Bell | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251607 | Input to draftCR Rel-19 TS 28.105 Use case on AIML prediction latency in training | Nokia, Nokia Shanghai Bell | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251608 | Input to draftCR Rel-19 TS 28.105 Use case on ML explainability for inference | Nokia, Nokia Shanghai Bell | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251609 | Input to draftCR Rel-19 TS 28.105 Use case on ML explainability for training | Nokia, Nokia Shanghai Bell | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251610 | Input to draftCR Rel-19 TS 28.105 Solution on model confidence requirement | Nokia, Nokia Shanghai Bell | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251611 | Input to draftCR Rel-19 TS 28.105 Solution on sustainable AIML training | Nokia, Nokia Shanghai Bell | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251612 | Input to draftCR Rel-19 TS 28.105 Use case on model confidence requirement | Nokia, Nokia Shanghai Bell | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251613 | Input to draftCR Rel-19 TS 28.105 Use case on sustainable AIML training | Nokia, Nokia Shanghai Bell | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251614 | Input to draftCR Rel-19 TS 28.105 Add RL NRMs | Nokia, Nokia Shanghai Bell | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251633 | Rel-19 Input to draftCR TS 28.105 Add NRMs on distributed training | CATT | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251713 | Input to DraftCR Rel-19 TS 28.105 Fix wrong reference and add RRC report | Ericsson GmbH, Eurolab | other | Agreement | Yes |
No
| available | No | ||||
S5‑251755 | pCR DraftCR Rel-19 TS 28.105 Editorials corrections to the requirements of Managing ML models in use in a live network | NEC Europe Ltd | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251756 | Input to Draft CR Rel-19 CR TS 28.105 Pre-specialized training and Fine-tuning | NEC, Intel | draftCR | Approval | Yes |
No
| available | No | ||||
S5‑251757 | Input to draft CR TS 28.105 add NRM for ML pre-training and fine-tuning | NEC, Intel | draftCR | Approval | Yes |
No
| available | No | ||||
6.19.2 | Study on Management Data Analytics (MDA) – Phase 3 (completed) | |||||||||||
6.19.2.1 | Management Data Analytics phase 3 | S5‑251317 | Add the use case and requirements for edge application deployment location analysis | AsiaInfo, ZTE | CR | Approval | Yes |
No
| available | No | ||
S5‑251318 | Add the use case and requirements for edge computing performance analysis | AsiaInfo, ZTE | CR | Approval | Yes |
No
| available | No | ||||
S5‑251319 | Add the use case and requirements for traffic congestion prediction analytics based on UE throughput | AsiaInfo, ZTE | CR | Approval | Yes |
No
| available | No | ||||
S5‑251320 | Rel-19 CR TS 28.104 Add solution for edge application deployment location analysis | AsiaInfo, ZTE | CR | Approval | Yes |
No
| available | No | ||||
S5‑251321 | Rel-19 CR TS 28.104 add solutions for edge computing performance analysis | AsiaInfo, ZTE | CR | Approval | Yes |
No
| available | No | ||||
S5‑251440 | Rel19 CR TS28.104 add solution on management data correlation analytics | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251441 | Rel19 CR TS28.104 add solution on correlation analytics for NF Scaling and dimensioning | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251442 | Rel19 CR TS28.104 add solution on management data correlation analytics for threshold assessment and adjustment | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251443 | Rel19 CR TS28.104 add solution on management data collection recommendation for predicted failures | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251462 | Rel-19 CR TS 28.104 Add solutions for traffic congestion prediction analysis based on UE throughput | AsiaInfo, ZTE | CR | Approval | Yes |
No
| available | No | ||||
S5‑251539 | Rel-19 CR 28.104 software upgrade validation | Samsung R&D Institute UK | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251554 | Rel-19 CR TS 28.104 update MDA type for UE throughput anlaysis | Huawei | CR | Approval | Yes |
No
| available | No | ||||
S5‑251555 | Rel-19 CR TS 28.104 add stage3 solution for mobility performance analysis | Huawei, Samsung | CR | Approval | Yes |
No
| available | No | ||||
S5‑251596 | Rel-19 CR TS 28.104 Improvements to failure prediction | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251618 | Rel-19 CR 28.104 adding statics information in failure prediction output | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251619 | Rel-19 CR 28.104 clarification on resource management | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251620 | Rel-19 CR 28.104 topology information as enabling data is missing | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251626 | Rel 19 CR TS 28.104 Clarify definition of confidenceDegree attribute | Ericsson | CR | Approval | Yes |
No
| available | No | ||||
S5‑251715 | Rel-19 CR TS 28.104 Fix wrong reference and add RRC report | Ericsson GmbH, Eurolab | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251736 | Rel-19 CR TS 28.104 Multi Domain Resource Optimization | Nokia | CR | Approval | Yes |
No
| available | No | ||||
6.19.3 | Study on intent driven management services for mobile network phase 3 (completed) | |||||||||||
6.19.3.1 | Intent driven management services for mobile network phase 3 | S5‑251241 | Enhancing Enablers for Intent Fulfilment | Nokia | pCR | Approval | Yes |
No
| available | No | ||
S5‑251272 | Rel-19 CR TS 28.312 Update the solution for Intent capability exposure | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251273 | Rel-19 CR TS 28.312 Update the solution for intent negotiation report | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251274 | Rel-19 CR TS 28.312 Enhance the use case and solution to support radio network support for UAV pre-flight preparation | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | S5‑250833 | |||
S5‑251275 | Rel-19 CR TS 28.312 Add procedure for intent exploration | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251276 | Rel-19 CR TS 28.312 Update procedures for intent report management to support implicit intent report subscription | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251277 | Rel-19 CR TS 28.312 Update 5.3.1 Intent handling capability obtaining | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251278 | Rel-19 CR TS 28.312 Add missing abbreviation and definition | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251279 | Rel-19 CR TS 28.312 Enhance the definition for intentMgmtPurpose | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251280 | Rel-19 CR TS 28.312 Enhance the solution for RadioServiceExpectation | Huawei, Deutsche Telekom | CR | Yes |
No
| available | No | |||||
S5‑251281 | Rel-19 Address the implementation issue for CR 0277 and CR 0304 | Huawei | CR | Agreement | No |
Yes
| withdrawn | Yes | ||||
S5‑251367 | Rel-19 CR TS 28.312 Enhance the use case and solution to support MOCN undifferentiated radio service in a specified area | China Unicom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251392 | Rel-19 CR TS 28.312 Update clause 6.1 and 7.1 to support intent negotiation | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251408 | Rel-19 CR TS 28.312 Add Stage-3 Solution for intent driven management of network maintenance | NTT DOCOMO | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251422 | Rel-19 CR 28.312 Add generic utility function support (stage 2) | Ericsson Inc. | CR | Approval | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251445 | Rel-19 CR TS 28.312 Add requirements and solutions for refusing to intent negotiation | China Mobile Com. Corporation | CR | Yes |
Yes
| withdrawn | Yes | |||||
S5‑251446 | Rel-19 CR TS 28.312 Add description of excavating of implicit intent | China Mobile Com. Corporation | CR | Yes |
Yes
| withdrawn | Yes | |||||
S5‑251449 | Rel-19 CR TS 28.312 Update on Intent Negotiation Use Case | ZTE Corporation | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251450 | Rel-19 CR TS 28.312 Update on Intent Negotiation NRM | ZTE Corporation | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251458 | Rel-19 CR TS 28.312 Add requirements and solutions for triggering intent negotiation | China Mobile Com. Corporation | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251460 | Rel-19 CR TS 28.312 Add description of excavating of implicit intent | China Mobile Com. Corporation | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251494 | Rel-19 CR TS 28.312 Modify the Generic Information model definition | China Mobile, Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251495 | Rel-19 CR TS 28.312 Update solution for intent exploration | China Mobile, Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251532 | Rel-19 CR TS 28.312 Add use case and requirement for intent related intents | NTT DOCOMO | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251534 | Rel-19 CR TS 28.312 Add an example to support intent report based on condition | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251559 | Rel-19 CR TS 28.312 Correction on introduction in clause 5.1.9.1 | NTT DOCOMO | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251577 | Rel-19 CR TS 28.312 Correction on introduction for intent fulfilment feasibility check | NTT DOCOMO | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251603 | Rel-19 CR 28.312 Clarifications on negotiation of intent fulfillment | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251660 | Rel-19 CR TS 28.312 Introduce mapping table | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251661 | Rel-19 CR TS 28.312 Update UML diagram for intent | Ericsson, ZTE | CR | Approval | Yes |
No
| available | No | ||||
S5‑251750 | Rel-19 CR 28.312 Add generic utility function support (stage 2) | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
6.19.4 | Study on closed control loop management (completed) | S5‑251334 | TS28.536 CR update Assurace CCL model | Nokia Americas | CR | Agreement | Yes |
No
| available | No | ||
6.19.4.1 | Closed Control Loop Management | S5‑251242 | CCL Goal-targets and actions conflicts | Nokia, Samsung | pCR | Approval | Yes |
No
| available | No | ||
S5‑251243 | CCL network & time scope conflicts | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251244 | CCL Trigger conflicts | Nokia, Samsung | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251245 | CCL Indirect target conflicts | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251246 | CCL-impact assessment and resolution | Nokia, Samsung | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251247 | CCL decision escalation | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251248 | Coordinating CCLs with other functions | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251249 | CCL General NRM | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251250 | DP on CCL and ACCL modelling relationship | Nokia | discussion | Endorsement | Yes |
No
| available | No | ||||
S5‑251251 | CCL coordination NRM | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251252 | Informative Annex on conflict handling approach | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251527 | Rel-19 pCR 28.567 Triggered CCL UC and Requirements | Samsung R&D Institute UK | pCR | Agreement | Yes |
No
| available | No | ||||
S5‑251536 | pCR TS 28.567 Add use case and requirements for network performance problem recovery | Huawei, Deutsche Telekom | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251662 | Rel-19 CR TS 28.536 Clarify generic use of closed control loop | Ericsson, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251663 | pCR on TS 28.567 introduce imported information elements | Ericsson, Deutsche Telekom | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251749 | Rel-19 pCR TS 28.567 Procedure and metrics for CCL performance monitoring | Samsung Electronics GmbH | pCR | Approval | Yes |
No
| available | No | ||||
6.19.5 | Study on management aspects of Network Digital Twin (completed) | |||||||||||
6.19.5.1 | Management aspects of Network Digital Twins | S5‑251253 | NDT concept and scope | Nokia, Ericsson | pCR | Approval | Yes |
No
| available | No | ||
S5‑251254 | NDT relation to automation | Nokia, Ericsson | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251255 | NDTs for verification | Nokia, Ericsson | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251256 | NDT support to Automation | Nokia, Ericsson | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251257 | NDT NRM | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251423 | Discussion Paper Justification for the Inclusion of Nested NDT Definition in the TS 28.561 | FiberCop, Deutsche Telekom, Telecom Italia | discussion | Endorsement | Yes |
No
| available | No | ||||
S5‑251427 | Pseudo-CR on TS 28.561 Nested NDT Definition | FiberCop, Deutsche Telekom, Telecom Italia | pCR | Approval | Yes |
Yes
| revised | No | S5‑251657 | |||
S5‑251447 | Rel-19 pCR TS 28.561 Generic NDT NRM | ZTE Corporation | pCR | Agreement | Yes |
No
| available | No | ||||
S5‑251448 | Rel-19 pCR TS 28.561 Add Requirements for Network failure and risk prediction | ZTE Corporation | pCR | Agreement | Yes |
No
| available | No | ||||
S5‑251490 | TS28.561 Add the NDT concept and scope | China Mobile | pCR | Approval | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251491 | TS28.561 NDT support for network automation | China Mobile, Huawei | pCR | Approval | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251492 | pCR Add UC and requirements of using NDT to generate customer experience data for TS 28.561 | China Mobile, Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251493 | pCR Add solution of Using NDT to generate ML training data for TS 28.561 | China Mobile | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251538 | Rel-19 pCR 28.561 adding requirement of network issue inducement capability | NTT DOCOMO, SK Telecom | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251540 | Rel-19 pCR 28.561 NDT overview | NTT DOCOMO, SK Telecom | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251542 | Rel-19 CR 28.561 NDT Inducement Requirements | Samsung R&D Institute UK | pCR | Yes |
No
| available | No | |||||
S5‑251566 | Pseudo-CR on TS 28.561 Use case of RAN energy saving policy verification | Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251567 | Pseudo-CR on TS 28.561 NDT NRMs | Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251568 | Pseudo-CR on TS 28.561 Remove abbreviations in clause 5.1 | Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251569 | Pseudo-CR on TS 28.561 Add requirements for NDT supporting data generation | Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251570 | Pseudo-CR on TS 28.561 Procedure for consuming NDT capability | Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251599 | Rel-19 pCR TS 28.561 General improvements to use cases and requirements | Huawei Tech. Japan, K.K. | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251601 | TS28.561 Add the NDT concept and scope | China Mobile, FiberCop | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251602 | TS28.561 NDT support for network automation | China Mobile, Huawei, FiberCop | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251648 | Pseudo-CR on TS 28.561 Update use case for NDT support analysis of failure events including signaling storm | Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251657 | Pseudo-CR on TS 28.561 Nested NDT Definition | FiberCop, Deutsche Telekom, Telecom Italia, Orange | pCR | Approval | Yes |
No
| available | No | S5‑251427 | |||
6.19.6 | Study on Cloud Aspects of Management and Orchestration | S5‑251262 | pCR TR 28.869 Annex example for CRD based deployment | Rakuten Mobile, Inc | pCR | Approval | Yes |
No
| available | No | ||
S5‑251263 | pCR TR 28.869 LCM changes for declarative descriptor | Rakuten Mobile, Inc | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251537 | pCR TR 28.869 Add potential solution for VNF configuration management | Huawei, Deutsche Telekom, Ericsson, Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251560 | R19 pCR TR 28.869 enhance observability requirements (Use case 7) | Orange, AT&T | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251571 | Pseudo-CR on TR 28.869 Add an example in Annex B | Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251572 | Pseudo-CR on TR 28.869 Add conclusion for management data streaming solution based on message bus | Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251578 | pCR Add evaluation for solutions in clause 5.2.1.3 | China Mobile,NTT DOCOMO | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251579 | pCR Add solution and evaluation statement for usecase Placement of cloud native NFs | China Mobile | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251583 | pCR TR 28.869 Cloud-native VNF policy management evaluation | NTT DOCOMO | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251584 | pCR TR 28.869 3GPP management architecture evolution based on PaaS | NTT DOCOMO, China Mobile | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251594 | pCR Add evaluation for some LCM solutions and update the clause 5.2.6 | China Mobile | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251600 | pCR Add general conclusion and some recommendations | China Mobile | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251639 | pCR Add terminology | China Mobile | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251718 | pCR TR 28.869 Adopt NF Deployment terminology in scaling use case | Ericsson Telecomunicazioni SpA | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251719 | pCR TR 28.869 Detail procedure flow for creation of NF Deployment | Ericsson Telecomunicazioni SpA | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251722 | pCR TR 28.869 Specification structure for LCM of NF Deployment | Ericsson Telecomunicazioni SpA | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251725 | pCR TR 28.869 Update Annex D for example scenario for creation of NF Deployment instance | Ericsson Telecomunicazioni SpA | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251744 | DP cloud native NF data streaming - connection based vs pub-sub based | Rakuten Mobile, Inc | discussion | Endorsement | Yes |
No
| available | No | ||||
S5‑251746 | Pseudo-CR on enhance annex examples for data streaming for cloud native network function | Rakuten Mobile, Inc | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251747 | Pseudo-CR on Add evaluation and conclusion for management data streaming based on message bus | Rakuten Mobile, Inc | pCR | Approval | Yes |
No
| available | No | ||||
6.19.7 | Study on Enablers for Security Monitoring (completed) | |||||||||||
6.19.8 | Study on Service Based Management Architecture enhancement phase 3 (completed) | |||||||||||
6.19.8.1 | Service Based Management Architecture enhancement phase 3 | S5‑251333 | Rel-19 CR 28.532 Add new notifications for reliability | Ericsson India Private Limited | CR | Approval | No |
Yes
| withdrawn | Yes | ||
S5‑251393 | Rel-19 CR TS 28537 Add requirements for discovering management capabilities of MnS instances based on area of interest | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | S5‑250881 | |||
S5‑251394 | Rel-19 CR TS 28.622 Extend the MnsScope to support area of interest (Stage2) | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | S5‑250882 | |||
S5‑251395 | Rel-19 CR TS 28.623 Extend the MnsScope to support area of interest (Stage3) | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | S5‑250883 | |||
S5‑251396 | Rel-19 CR TS 28.622 Enhance the MnSInfo to support discovery of management capabilities of MnS supported by a MnS Producer (Stage2) | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251397 | Rel-19 CR TS 28.623 Enhance the MnSInfo to support discovery of management capabilities of MnS supported by a MnS Producer (Stage3) | Huawei, Deutsche Telekom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251486 | Rel-19 CR TS 28.111 Update terms and concepts overview | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251487 | Rel-19 CR TS 28.111 Update references and abbreviations | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251488 | Rel-19 CR TS 28.111 Update scope | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251581 | Rel-19 CR 32.158 Add details for MnS API versioning | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251582 | Rel-19 CR 28.537 Add details for MnS API versioning | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251675 | Discussion paper on adding information in entry point specifications | Ericsson, Huawei, Deutsche Telekom | discussion | Information | Yes |
No
| available | No | ||||
S5‑251676 | Rel-19 CR TS 28.310 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251677 | Rel-19 CR TS 28.313 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251678 | Rel-19 CR TS 28.314 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251679 | Rel-19 CR TS 28.404 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251680 | Rel-19 CR TS 28.531 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251681 | Rel-19 CR TS 28.532 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251682 | Rel-19 CR TS 28.535 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251683 | Rel-19 CR TS 28.537 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251684 | Rel-19 CR TS 28.540 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251685 | Rel-19 CR TS 28.555 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251686 | Rel-19 CR TS 28.622 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251687 | Rel-19 CR TS 28.130 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251688 | Rel-19 CR TS 32.421 Add entry point information | Ericsson, Huawei, Deutsche Telekom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251724 | Rel-19 CR TS 28.533 Update Annex E | Ericsson GmbH, Eurolab | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251733 | Rel-19 CR 28.532 Add new notifications for reliability | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251743 | Rel-19 CR 28.532 Update notifications with common header | Ericsson India Private Limited | CR | Approval | Yes |
No
| available | No | ||||
S5‑251752 | Rel-19 CR 28.622 Reliable notification transfer | Ericsson Hungary Ltd | CR | Approval | Yes |
No
| available | No | S5‑250888 | |||
6.19.9 | Study on Management of planned configurations (completed) | |||||||||||
6.19.9.1 | Management of planned configurations | S5‑251635 | Rel-19 pCR TS 28.572 Improve clauses on Planned configuration concepts | Nokia | pCR | Approval | Yes |
No
| available | No | ||
S5‑251636 | Rel-19 pCR TS 28.572 Improve clauses on Managing planned configurations | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251637 | Rel-19 pCR TS 28.572 Improve clause Information model | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251638 | Rel-19 pCR TS 28.572 Improve clause RESTful HTTP-based solution set | Nokia | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251694 | Rel-19 pCR TS 28.572 Allow recursive Planned configuration groups | Ericsson India Private Limited | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251751 | Rel-19 pCR TS 28.572 Plan Configuration Examples | Ericsson India Private Limited | pCR | Approval | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251753 | Rel-19 pCR TS 28.572 Plan Activation Results | Ericsson India Private Limited | pCR | Approval | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251754 | Discussion paper on: Long Running Configuration Reads | Ericsson India Private Limited | discussion | Endorsement | Yes |
Yes
| withdrawn | Yes | ||||
6.19.10 | Data management phase 2 | S5‑251499 | Input to Draft CR 28.622 External Management Data | Nokia | other | Approval | Yes |
No
| available | No | ||
6.19.11 | Study on data management regarding subscriptions and reporting (completed) | |||||||||||
6.19.11.1 | Data management regarding subscriptions and reporting | S5‑251231 | Rel-19 CR TS 28.405 QoE Reference Uniqueness | Ericsson | CR | Agreement | Yes |
No
| available | No | ||
S5‑251232 | Rel-19 CR TS 32.422 Trace Reference Uniqueness | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251401 | Rel-19 CR TS 32.422 Introduction of new Trace Depth “Micro” for Optimised Tracing | Jio Platforms Ltd (JPL) | CR | Decision | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251501 | Rel-19 CR TS 32.421 Enhancement to Trace Reference | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251502 | Rel-19 CR TS 32.422 Enhancement to Trace Reference | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251503 | Rel-19 CR TS 32.423 Enhancement to Trace Reference | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251504 | Rel-19 CR TS 28.622 Enhancement to Trace Reference | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251505 | Rel-19 CR TS 28.623 Enhancement to Trace Reference | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251524 | Rel-19 CR TS 32.422 Introduction of new Trace Depth “Micro” for Optimised Tracing | Jio Platforms Ltd (JPL) | CR | Approval | Yes |
No
| available | No | ||||
6.19.12 | 5G performance measurements and KPIs phase 4 | S5‑251224 | Rel-19 CR TS 28.532 PM File extension | Ericsson LM | CR | Agreement | Yes |
Yes
| withdrawn | Yes | ||
S5‑251225 | Rel-19 CR 28.558 misaligned 5GC UE level measurement procedure | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251227 | Rel-19 CR TS 28.552 Cell Unavailable Time performance measurement | Ericsson, AT&T, Samsung | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251228 | Rel-19 CR TS 32.401 PM Counter Metadata | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251229 | Rel-19 CR TS 32.404 PM Counter Metadata | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251653 | Rel-19 CR TS 28.552 Correction of Distribution of time interval | Esurfing IoT | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251654 | Rel-19 CR TS 28.552 Add Multicast Group Paging records for MBS measurement | Esurfing IoT | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251658 | Rel-19 CR TS 28.552 add measurement of coverage satisfaction ratio | CMCC, Huawei, ZTE, CATT | CR | Approval | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251709 | Rel-19 CR TS 28.554 add measurement of coverage satisfaction ratio | CMCC, Huawei, ZTE, CATT | CR | Approval | No |
Yes
| withdrawn | Yes | ||||
S5‑251710 | Rel-19 CR TS 28.552 add measurement of coverage satisfaction ratio | CMCC, Huawei, ZTE, CATT | CR | Approval | No |
Yes
| withdrawn | Yes | ||||
S5‑251712 | Rel-19 CR TS 28.552 add measurement of coverage ratio | CMCC, Huawei, ZTE, CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251714 | Rel-19 CR TS 28.554 add measurement of coverage ratio | CMCC, Huawei, ZTE, CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251735 | Rel-19 CR TS 28.532 PM File extension | Ericsson LM | CR | Agreement | Yes |
No
| available | No | ||||
6.19.13 | 5G Advanced NRM features phase 3 | S5‑251292 | Rel19 CR TS28.541 NRM enhancements to ManagedNFProfile | Nokia, Nokia Shanghai Bell, ZTE Corporation, Orange | CR | Agreement | Yes |
No
| available | No | ||
S5‑251293 | Rel19 CR TS28.541 change the dataType concerning HostAddr | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251294 | Rel19 CR TS28.538 change the dataType concerning HostAddr | Nokia, Nokia Shanghai Bell | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251398 | Rel-19 CR TS 28.541 update the naming convention in TS28541_NrNrm.yaml to align with stage 2 definition | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251399 | Rel-19 CR TS 28.622 Address the misalignment issues for vnfParametersList and peeParametersList (stage2) | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251400 | Rel-19 CR TS 28.623 Address the misalignment issues for vnfParametersList and peeParametersList (stage3) | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251402 | Rel-19 CR TS 28.622 Enhance the definition for schedulerStatus and conditionStatus with default values (stage2) | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251403 | Rel-19 CR TS 28.623 Enhance the definition for schedulerStatus and conditionStatus with default values (stage3) | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251404 | Rel-19 CR TS 28.540 Enhance the requirement description | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251573 | Rel-19 CR TS 28.540 Add requirements for management of Ambient IoT | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251574 | Rel-19 CR TS 28.541 Add AIOTF and ADM IOC to support management of Ambient IoT | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251575 | Rel-19 CR TS 28.538 Update the procedure 5GC NF Provisioning | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251589 | Rel-19 CR 28.662 Update sector equipment and antenna function definitions | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251590 | Rel-19 CR 28.541 Update sector equipment and antenna function definitions | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251711 | Rel-19 CR 28.623 Update sector equipment and antenna function definitions | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251720 | DP on Solution-agnostic request for service provisioning | Ericsson GmbH, Eurolab | discussion | Endorsement | Yes |
No
| available | No | ||||
S5‑251721 | Rel-19 CR TS 28.541 Enhance network slicing model to support solution-agnostic service provisioning request. | Ericsson GmbH, Eurolab | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251723 | Rel-19 CR TS 28.531 Add requirements to support solution-agnostic request for service provisioning | Ericsson GmbH, Eurolab | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251728 | Rel-19 CR TS 28.622 Remove stage-3 clarifications for Float datatype | Ericsson GmbH, Eurolab | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251731 | Rel-19 CR 28.663 Update sector equipment and antenna function definitions | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
6.19.14 | Subscriber and Equipment Trace and QoE collection management | S5‑251238 | Rel-19 CR TS 32.423 Corrections on Trace Record Format | Ericsson, AT&T | CR | Agreement | Yes |
No
| available | No | ||
S5‑251375 | Introduction of Sequence Number in Trace Record Header | Jio Platforms Ltd (JPL) | CR | Decision | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251378 | Rel-19 CR TS 32.423 Introduction of Sequence Number in Trace Record Header | Jio Platforms Ltd (JPL) | CR | Decision | Yes |
No
| available | No | ||||
S5‑251388 | Additional NFs added in Trace Record contents | Jio Platforms Ltd(JPL) | CR | Decision | Yes |
No
| available | No | ||||
S5‑251405 | Introduction of Summary Code in Trace Record Header for Optimised Tracing | Jio Platforms Ltd (JPL) | CR | Decision | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251525 | Rel-19 CR TS 32.423 Introduction of Summary Code in Trace Record Header for Optimised Tracing | Jio Platforms Ltd (JPL) | CR | Approval | Yes |
No
| available | No | ||||
6.19.15 | Study on Management Aspects of NTN Phase 2 (completed) | |||||||||||
6.19.15.1 | Management Aspects of NTN Phase 2 | S5‑251454 | Rel-19 CR TS 28.541 Add attributes to support MEC deployment on board the NTN | ZTE Corporation | CR | Approval | Yes |
No
| available | No | ||
S5‑251528 | CR 28.657 Add requirements for SnF support | Samsung R&D Institute UK | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251556 | Rel-19 CR TS 28.540 Add new requirements for management of NTN | China Unicom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251576 | Rel-19 CR TS 28.541 add YAML stage 3 for NTN time based solution | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251585 | Rel-19 CR 28.540 Add secure backhaul requirements for NTN | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251586 | Rel-19 CR 28.541 Add solution for NTN time-based IP configuration | Ericsson Canada Inc. | CR | Approval | Yes |
No
| available | No | ||||
S5‑251588 | Rel-19 CR 28540 Add NTN regenerative concepts and requirements | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251629 | Rel-19 CR TS 28.658 Add attributes to support Store and Forward Satellite operation for eNB | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251630 | Rel-19 CR TS 28.658 Add attributes to support Store and Forward Satellite operation for eNB stage3 | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251631 | Rel-19 CR TS 28.708 Add attributes to support Store and Forward Satellite operation for EPC | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251632 | Rel-19 CR TS 28.709 Add attributes to support Store and Forward Satellite operation for EPC stage3 | CATT | CR | Approval | Yes |
No
| available | No | ||||
6.19.16 | Study on management of IAB nodes (completed) | |||||||||||
6.19.16.1 | Management of IAB nodes | S5‑251656 | Requirements for IAB-node connects to management system | Ericsson | CR | Approval | Yes |
No
| available | No | ||
S5‑251695 | Use case IAB-node connects to management system | Ericsson | CR | Approval | Yes |
No
| available | No | ||||
S5‑251708 | Procedure IAB-node connects to management system | Ericsson | CR | Approval | Yes |
No
| available | No | ||||
6.19.17 | Study on management aspects of RedCap feature(completed) | |||||||||||
6.19.17.1 | Management Aspects of RedCap features | S5‑251455 | Rel-19 CR TS28.552 Enhance RRC connection resuming related measurements for RedCap UEs | ZTE Corporation | CR | Approval | Yes |
No
| available | No | ||
S5‑251456 | Rel-19 CR TS28.552 Enhance PRB Usage related measurements for RedCap UEs | ZTE Corporation | CR | Approval | Yes |
No
| available | No | ||||
S5‑251457 | Rel-19 CR TS28.552 Enhance Number of Active UEs related measurements for RedCap UEs | ZTE Corporation | CR | Approval | Yes |
No
| available | No | ||||
S5‑251745 | Rel-19 CR TS 28.540 Adding requirement to control RedCap and e-RedCap UEs access based on network conditions | Samsung Electronics GmbH | CR | Approval | Yes |
No
| available | No | ||||
S5‑251748 | Rel-19 CR TS 28.541 Enhancing NR NRM to control RedCap and e-RedCap UEs access | Samsung Electronics GmbH | CR | Approval | Yes |
No
| available | No | ||||
6.19.18 | Study on Enhancement of Management Aspects related to NWDAF Phase 2 (completed) | |||||||||||
6.19.18.1 | Enhancement of Management Aspects related to NWDAF Phase 2 | S5‑251336 | Rel-19 CR 28.552 Add a new measurement related to efficiency of data collection from NFs performed by NWDAF | China Telecom | CR | Approval | Yes |
No
| available | No | ||
S5‑251337 | Rel-19 CR 28.552 Add a new measurement related to efficiency of data collection from DCCF or NWDAF hosting DCCF performed by NWDAF | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251338 | Rel-19 CR 28.552 Add a new measurement related to transmission rate related to the data collection from NFs performed by NWDAF | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251339 | Rel-19 CR 28.552 Add a new measurement related to transmission rate related to the data collection from DCCF or NWDAF hosting DCCF performed by NWDAF | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251340 | Rel-19 CR 28.552 Add use case descriptions on monitoring of NWDAF data collection | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
6.19.19 | Study on Management of Network Sharing Phase 3 (completed) | |||||||||||
6.19.19.1 | Management of Network Sharing Phase 3 | S5‑251374 | Rel-19 CR TS 32.130 Enhance the service-based management architecture for MOCN | Huawei, China Unicom | CR | Agreement | Yes |
No
| available | No | ||
S5‑251376 | Rel-19 CR TS 32.130 Enhance Indirect Network Sharing scenario description | Huawei, China Unicom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251377 | Rel-19 CR TS 32.130 Clarify MOCN and GWCN scenarios description | Huawei, China Unicom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251379 | Rel-19 CR TS 32.130 Categorize requirements for the management support for Indirect Network Sharing scenario | Huawei, China Unicom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251381 | Rel-19 CR TS 32.130 Separate business-level requirements from specification-level requirements | Huawei, China Unicom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251650 | Rel-19 CR TS 28.541 Add support of RAN configurations for Indirect Network Sharing | China Unicom | CR | Agreement | No |
Yes
| withdrawn | Yes | ||||
S5‑251651 | Rel-19 CR TS 32.130 Update abbreviations for Indirect Network Sharing | China Unicom, China Telecom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251655 | Rel-19 CR TS 28.541 Add solution to support RAN configurations for Indirect Network Sharing | China Unicom, China Telecom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251732 | Rel-19 CR TS 32.130 Add PLMN granularity performance measurement requirements for Indirect Network Sharing | Esurfing IoT, China Unicom | CR | Agreement | Yes |
No
| available | No | ||||
6.19.20 | Study on energy efficiency and energy saving aspects of 5G networks and services (completed) | |||||||||||
6.19.20.1 | Energy efficiency and energy saving aspects of 5G networks and services | S5‑251264 | Rel-19 CR TS 28.310 Introduce energy supply, carbon emission and renewable energy information elements | Nokia | CR | Agreement | Yes |
No
| available | No | ||
S5‑251265 | Rel-19 CR TS 28.622 Add GenericCollection to support grouping of objects for energy related information - Stage 2 | Nokia | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251266 | Rel-19 CR TS 28.623 Add GenericCollection to support grouping of objects for energy related information - Stage 3 | Nokia | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251267 | Rel-19 CR TS 28.532 Introduce energy supply, carbon emission and renewable energy information elements - stage 3 impacts | Nokia | CR | Agreement | No |
Yes
| withdrawn | Yes | ||||
S5‑251268 | Rel-19 CR TS 28.310 Multi-carrier RAN energy saving optimization | Nokia | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251269 | Rel-19 CR TS 28.104 Enhance the MDA assisted Energy Saving use case for handling of power shortages | Nokia | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251270 | Discussion on modelling of energy-related information | Nokia | discussion | Information | Yes |
No
| available | No | ||||
S5‑251271 | DP on TS 28.554 KPIs related to NF Energy Consumption | Nokia | discussion | Endorsement | No |
Yes
| withdrawn | Yes | ||||
S5‑251335 | Incorporation of conclusions from TR 28.880 | Vodafone | CR | Approval | Yes |
No
| available | No | ||||
S5‑251386 | Rel-19 CR TS 28.310 Add information model definitions for energy related information | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
6.19.21 | Study on Enhanced OAM for management exposure to external consumers (completed) | |||||||||||
6.19.21.1 | Enhanced OAM for management service exposure to external consumers through CAPIF | S5‑251373 | Rel-19 pCR TS 28.579 Introduce definition of External MnS consumer | Huawei | pCR | Approval | Yes |
No
| available | No | ||
S5‑251483 | pCR TS 28.579 Add concepts content | Huawei, Nokia, Samsung | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251484 | DP on management services exposure | Huawei | discussion | Endorsement | Yes |
No
| available | No | ||||
S5‑251485 | pCR TS 28.579 Introduce MSEDF | Huawei | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251696 | Discussion paper on MSED components, requirements and naming | Nokia Hungary | discussion | Endorsement | Yes |
No
| available | No | ||||
S5‑251697 | Rel-19 pCR TS 28.579 Add use case and requirements for registration of the MSED into the CCF | Nokia Hungary | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251698 | Rel-19 pCR TS 28.579 Add use case solution for registration of the MSED into the CCF | Nokia Hungary | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251699 | Rel-19 pCR TS 28.579 Add use case requirements for publishing of management services to the CCF | Nokia Hungary | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251700 | Rel-19 pCR TS 28.579 Add use case solution to enable the publishing management services to the CCF | Nokia Hungary | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251701 | Rel-19 pCR TS 28.579 Add use case requirements for logging of management service APIs invocations to the CCF | Nokia Hungary | pCR | Approval | Yes |
No
| available | No | ||||
S5‑251702 | Rel-19 pCR TS 28.579 Add use case solution for logging the management service API invocations to the CCF | Nokia Hungary | pCR | Approval | Yes |
No
| available | No | ||||
6.19.22 | Management for MonStra (completed) | S5‑251734 | Correction of the description of the attribute stmTargetUri | Nokia Germany | CR | Yes |
No
| available | No | |||
7 | Charging | |||||||||||
7.1 | Charging Plenary | S5‑251215 | agenda_with_Tdocs_sequence_CH | SWG CH Chair (MATRIXX Software) | agenda | No |
No
| reserved | No | |||
S5‑251216 | Charging exec report | SWG CH Chair (MATRIXX Software) | report | No |
No
| reserved | No | |||||
S5‑251217 | Collection of useful contributions and external communication documents in CH | SWG Vice Chair (Huawei Tech.(UK) Co.. Ltd) | other | No |
No
| reserved | No | |||||
S5‑251329 | Reply LS on Usage of Charging Characteristics and CHF Group ID | SA2 | LS in | Information | Yes |
No
| available | No | ||||
7.2 | New Charging Study/Work Item proposals | S5‑251368 | Revised WID on on Charging aspects of next generation real time communication services phase 2 | China Mobile | WID revised | Approval | Yes |
No
| available | No | ||
S5‑251433 | Rel-20 DP Moderator update on Charging Aspects of CAPIF | Nokia | discussion | Discussion | Yes |
No
| available | No | ||||
S5‑251463 | Moderated R20 topic discussion on use cases for charging reliability enhancement | Huawei | discussion | Discussion | Yes |
No
| available | No | ||||
S5‑251533 | Revised WID on Charging for Uncrewed Aerial Systems Phase 3 | China Mobile Com. Corporation | WID revised | Agreement | Yes |
No
| available | No | ||||
S5‑251535 | Discussion paper on objective for UAS_Ph3-CH | China Mobile Com. Corporation | discussion | Discussion | Yes |
No
| available | No | ||||
7.3 | Charging Maintenance and Rel-19 Charging small enhancements | S5‑251291 | Correct bindings information for 5G ProSe Charging | China Telecom | CR | Agreement | Yes |
No
| available | No | ||
S5‑251301 | Discussion on NSPA charging information correction | Huawei | discussion | Discussion | Yes |
No
| available | No | ||||
S5‑251302 | Rel-18 CR 28.201 Correction on NSPA charging information | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251303 | Rel-19 CR 28.201 Correction on NSPA charging information | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251304 | Rel-18 CR 28.201 Correction on NSPA charging information | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251305 | Rel-19 CR 28.201 Correction on NSPA charging information | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251306 | Rel-18 CR 32.298 Correction on NSPA charging information | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251307 | Rel-19 CR 32.298 Correction on NSPA charging information | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251371 | Rel-19 CR 28.851 Cleanup | China Mobile | CR | Approval | Yes |
Yes
| withdrawn | Yes | ||||
S5‑251434 | Rel-19 CR 28.849 EditHelp Editorial Changes | Nokia | CR | Approval | Yes |
No
| available | No | ||||
S5‑251508 | Rel-19 DP Handling of un-reported usage information after failure | Ericsson | discussion | Agreement | Yes |
No
| available | No | ||||
S5‑251526 | Rel-19 CR 28.851 Addressing editHelp comments | China Mobile | CR | Approval | Yes |
No
| available | No | ||||
S5‑251531 | Correction of reference | China Mobile Com. Corporation | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251604 | Rel-18 CR 32.298 Correction of API Information | Amdocs | CR | Approval | Yes |
No
| available | No | ||||
S5‑251605 | Rel-19 CR 32.298 Correction of API Information | Amdocs Software Systems Ltd | CR | Approval | Yes |
No
| available | No | ||||
7.4 | Rel-19 Work Items | |||||||||||
7.4.1 | CHF Segmentation | S5‑251464 | Discussion on the charging domain for NRF registration and discovery | Huawei | discussion | Discussion | Yes |
No
| available | No | ||
S5‑251465 | Rel-19 CR 32.291 Add charging domain for NRF registration and discovery | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251509 | Rel-19 CR 32.291 Addition of domain features | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251510 | Rel-19 CR 32.274 Addition of charging characteristics | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
7.4.2 | Charging Aspects of Ranging and Sidelink Positioning (completed) | |||||||||||
7.4.3 | Charging aspects for energy efficiency of network slice (completed) | |||||||||||
7.4.4 | Charging for indirect network sharing (completed) | |||||||||||
7.4.5 | Charging Aspects for 5G ProSe Ph3 | S5‑251299 | Correct bindings information for 5G ProSe Charging | China Telecom | CR | Agreement | Yes |
No
| available | No | ||
S5‑251300 | Correct bindings information for 5G ProSe Charging | China Telecom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251312 | Add layer 3 multi-hop ProSe UE-to-Network relay communication related attributes | China Telecom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251313 | Add layer 3 multi-hop ProSe UE-to-Network relay communication related CDR parameters | China Telecom | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251315 | Add information flows of Layer-3 ProSe UE-to-UE direct communication | China Telecom Corporation Ltd. | CR | Agreement | No |
Yes
| withdrawn | Yes | ||||
7.4.6 | Charging aspects of satellite access Phase 3 | S5‑251466 | Rel-19 CR 32.255 Addition of the Satellite Roaming Charging Principle | Huawei | CR | Agreement | Yes |
No
| available | No | ||
S5‑251580 | Update Business roles for Support of Satellite charging | CSCN, CATT | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251592 | Update Charging principles and architecture references for MVNOs charging | CSCN | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251640 | Introduce the support of store and forward satellite operation and UE-satellite-UE communication | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251641 | Add charging principle for store and forward satellite operation | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251642 | Add charging information for store and forward satellite operation of SMS service | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251643 | Add charging trigger for store and forward satellite operation with UP CIoT | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251644 | Add charging information for store and forward satellite operation with UP CIoT | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251645 | Add charging principle for UE-satellite-UE communication | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251646 | Add charging trigger and charging information for UE-satellite-UE communication | CATT | CR | Approval | Yes |
No
| available | No | ||||
S5‑251647 | Update reference for the TR | CATT | CR | Approval | Yes |
No
| available | No | ||||
7.4.7 | Charging aspects of CAPIF | S5‑251428 | CR 32.254 CAPIF Converged charging Architecture | Nokia | CR | Agreement | Yes |
No
| available | No | ||
S5‑251435 | Rel-19 CR 32.240 CAPIF Logical Charging Architecture | Nokia | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251436 | Rel-19 CR 32.240 CAPIF Service Charging | Nokia | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251437 | Rel-19 CR 32.240 CAPIF Reference Point | Nokia | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251467 | Rel-19 CR 32.254 Addition of the CAPIF Charging Architecture | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251468 | Rel-19 CR 32.254 Addition of the CAPIF Charging Principle and Scenarios | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251469 | Rel-19 CR 32.254 Addition of CAPIF charging support | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251511 | Rel-19 DP Charging architecture considerations for CAPIF | Ericsson | discussion | Agreement | Yes |
No
| available | No | ||||
S5‑251512 | Rel-19 CR 32.254 Addition of charging architecture for CAPIF | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251513 | Rel-19 CR 32.254 Addition of charging principles for CAPIF | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
7.4.8 | Charging aspects of next generation real time communication services phase 2 | S5‑251369 | Rel-19 CR 32.255 Support volume-based charging for standalone IMS data channel | China Mobile | CR | Approval | Yes |
No
| available | No | ||
S5‑251370 | Rel-19 CR 32.260 Support duration-based charging for standalone IMS data channel | China Mobile | CR | Approval | Yes |
No
| available | No | ||||
S5‑251470 | Rel-19 CR 32.260 Charging architecture for IMS DC application download charging charging | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251471 | Rel-19 CR 32.260 Charging principle for IMS DC application download charging | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251472 | Rel-19 CR 32.260 Charging information for IMS DC application download charging | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251473 | Rel-19 CR 32.291 Charging information for IMS DC application download charging | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251474 | Rel-19 CR 32.298 Charging information for IMS DC application download charging | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251475 | Rel-19 CR 32.260 Add duration based charging principle for DC application usage | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251476 | Rel-19 CR 32.255 Add volume based charging principle for DC application download and usage | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251477 | Rel-19 CR 32.255 Add volume based charging principle to support IMS DC as a PS Data Off Exempt Service | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251478 | Rel-19 CR 32.254 Add charging principle for IMS network capabilities exposure | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
7.4.9 | Charging for Uncrewed Aerial Systems Phase 2 | S5‑251514 | Rel-19 DP Format of user identity | Ericsson | discussion | Agreement | Yes |
No
| available | No | ||
S5‑251515 | Rel-19 CR 32.255 Addition of user identifiers | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
7.4.10 | Charging Aspects of 5GC LoCation Services | S5‑251341 | Extend the scope and charging architecture to support 5G LCS converged charging | China Telecom | CR | Approval | Yes |
No
| available | No | ||
S5‑251342 | Extend basic priciples, CDR generation and handling for 5G LCS converged charging | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251343 | Add message flow of converged charging for 5GC-MT-LR | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251344 | Add message flow of converged charging for 5GC-MO-LR | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251345 | Extend data description for 5G LCS converged charging | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251346 | Extend charging information and bindings for 5G LCS converged charging | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251347 | Extend Data Type for 5G LCS converged charging | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251348 | Extend CHF-CDR for 5G LCS converged charging | China Telecom | CR | Approval | Yes |
No
| available | No | ||||
S5‑251516 | Rel-19 CR 32.271 Addition of LCS architecture | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251517 | Rel-19 CR 32.271 Addition of charging architecture for LCS | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251518 | Rel-19 CR 32.271 Addition of charging principles for LCS | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
7.4.11 | Charging for Ambient power-enabled Internet of Things | S5‑251308 | Rel-19 CR 32.240 Add charging support for AIoT service | Huawei | CR | Agreement | Yes |
No
| available | No | ||
S5‑251309 | Rel-19 CR 32.254 Add charging support for AIoT service | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251310 | Rel-19 CR 32.291 Add charging support for AIoT service | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251311 | Rel-19 CR 32.298 Add charging support for AIoT service | Huawei | CR | Agreement | Yes |
No
| available | No | ||||
7.4.12 | Charging aspects for Multi-Operator Core Network (MOCN) network sharing | S5‑251519 | Rel-19 CR 32.240 Addition of MOCN network sharing | Ericsson | CR | Agreement | Yes |
No
| available | No | ||
S5‑251520 | Rel-19 CR 32.255 Addition of architecture for MOCN | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251521 | Rel-19 CR 32.256 Addition of architecture for network sharing | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251522 | Rel-19 CR 32.255 Addition of charging architecture for MOCN | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
S5‑251523 | Rel-19 CR 32.255 Addition of charging requirements for MOCN | Ericsson | CR | Agreement | Yes |
No
| available | No | ||||
7.5 | Charging Studies | |||||||||||
7.5.1 | Charging aspects of satellite access Phase 3 (completed) | |||||||||||
7.5.2 | Charging Aspects of CAPIF (completed) | |||||||||||
7.5.3 | Charging aspects of next generation real time communication services phase 2 (completed) | |||||||||||
7.5.4 | Charging aspects of Uncrewed Aerial Vehicle (completed) | |||||||||||
8 | Any Other Business | |||||||||||