Following modifications to the workplan were agreed at this meeting: ID 2233 on IMS, and its subparts, were changed to March plenary for completion 8/3-02. ID 1998 is now around 65%. Per to receive the dependency IETF draft new timeschedules from Ileana Leuca. Update the dependency draft list from tdoc 1336 (5 new ones). 3GPP wants the dates when the drafts are provided to IESG, but after that it can still be modifications to the drafts. The workplan is still to use that date however. Delayed drafts seems to be indicated for 100rel, privacy, and …? Subscribe notify draft has changed name to events. Version numbering on the drafts are not needed in the workplan. ID 1673 was completed 15/6-01. ID 1281 on multimedia capabilities is to be reviewed at CN#13 and is related with LS OUT N1-011051. Both this and the IDs 1282 and 1805 are not covered by any workitem,- and should be deleted unless requirements are received during CN#13. ID 1296 on interworking with other multimedia protocols has been progressed in N1 and this is marked with 5%. SIP compression is not in the workplan, and where to link this was discussed. ID 1653 on SIP emergency was not indicated as progressed in N1,- waiting for information from S2. N1s worktasks under this Building Block got the new deadline 8 March 2002. ID 1656 on AMR completed to about half now (50%), and is expected to be ready by plenary in December 2001. ID 526 on LCS needs more work on 24.008, estimated to have reached 80% now,- aiming for December 2001 plenary completion. ID 2254 on UE triggered authentication during connections is considered not to be done under ID 2099,- but instead it is recommended from N1 to delete this totally. ID 2248 on Iu flex,- N1 is waiting on S2. Is ID2247 needed since it is CN level ? ID 2556 on end to end QoS,- a question for N3 is if N1 related work task(s) are to be included (and also for other group(s)? ID 2510 under Display of Service Provider name on UE allocates CN as having the leading role. When the work has progressed sufficiently in S2 and a WG is needed it is proposed not to be N1. ID 2503 on Support of Presence Capability is allocated to the CN group. This should be allocated the WGs when the work has progressed sufficiently in S2.