Last Allocated Document: SP-130506

Temporary Documents List - Ordered by Agenda Item

Colour Key:
Agenda Item, Agenda Title
No Conclusion
Conclusion Reached
Document Revised
Document Withdrawn
Document Not Handled

The Hyperlinks are to the FTP server: ftp://ftp.3gpp.org/tsg_sa/TSG_SA/TSGS_61/Docs/

Created: 2013-09-12 06:43     START OF LIST

Agenda TD LongTitle Source Summary Doc_Type Doc_For Decision Rev_By Rev_Of LS_Source_file Comment Rx
1 - - - - - - - - - - -
2 - - - - - - - - - - -
2 SP-130332 Draft agenda for TSG SA meeting #61 TSG SA Chairman Draft agenda for TSG SA meeting #61 Agenda Approval Approved The TSG SA Chairman commented that the next meeting agenda should include Rel 13 items following the decisions for Rel 12 inclusion at this meeting and the items moved to Rel 13. The agenda was then approved. Y
3 - - - - - - - - - - -
4 - - - - - - - - - - -
4.1 - - - - - - - - - - -
4.1 SP-130333 Draft Report of TSG SA meeting #60 TSG SA Secretary Draft Report of TSG SA meeting #60 containing revision marks of changes on the distributed draft. Report Approval Approved The draft report was reviewed and approved. Y
4.2 - - - - - - - - - - -
5 - - - - - - - - - - -
5 SP-130408 1-week TSG setup TSG Chairs TSG#63 in March/2014 will be the initial trial for the 1-week setup From TSG#66 (Dec/2014) onwards all TSGs will be arranged on the same week Note: TSG GERAN will still be run separately This slideset pres [...]. Discussion Presentaton Noted Y
5 SP-130394 Managing TSG SA and TSG RAN overlapping meetings Telefonica The present contribution provides discussion material about the trial single-week TSG setup and presents issues relating to companies covering both TSG RAN and TSG SA with a small delegation. OTHER Discussion Noted Y
5.1 - - - - - - - - - - -
5.2 - - - - - - - - - - -
5.2 SP-130334 Prioritization Input to TSG SA#61 SA WG2 Chairman At TSG SA#61, TSG SA will review SA WG2 progress and make any decisions necessary to ensure success of approved work and study items. Time Budget vs. Available Time is highlighted as well as updated information [...]. DISCUSSION Discussion Noted These issues will be discussed in the prioritisation sessions and this contribution was then noted. Y
5.2 SP-130335 ProSe, GCSE_LTE and UPCON Analysis for Prioritization SA WG2 Chairman, SA WG1 Chairman To facilitate work rationalization at TSG SA#61, the complex features in SA WG2 work items ProSe, GCSE_LTE and UPCON are analyzed into component functionalities and dependencies, with time budget estimates asso [...]. DISCUSSION Discussion Revised SP-130337 Revised in SP-130337 Y
5.2 SP-130337 ProSe, GCSE_LTE and UPCON Analysis for Prioritization SA WG2 Chairman, SA WG1 Chairman To facilitate work rationalization at TSG SA#61, the complex features in SA WG2 work items ProSe, GCSE_LTE and UPCON are analyzed into component functionalities and dependencies, with time budget estimates asso [...]. DISCUSSION Discussion Noted SP-130335 The SA WG2 Chairman and SA WG1 Chairman were thanked for this analysis, which was then noted. Y
5.2 SP-130470 Summary of RAN decisions on system level features TSG RAN Chairman Outline: - Proximity Services (ProSe) - Group Communication (GCSE) - Uplink Congestion Control (UPCON) - Public Safety priorities for Rel 12 - 3GPP-WiFi Radio Interworking - MTC signalling enhancements. [...]. DISCUSSION Discussion Noted The TSG RAN Chairman was thanked for this contribution, which was then noted. Y
5.2 SP-130478 LS from TSG RAN: LS on Agreements from TSG RAN on work on Public Safety related use cases in Release 12 TSG RAN TSG RAN informs RAN WG1, RAN WG2, RAN WG3 and RAN WG4 that the attached document on Public Safety related use cases in Release 12 has been endorsed. LS In Information Noted RP-131405 Y
5.2 SP-130483 Required clarifications and guidance in view of the RAN prioritization decisions on ProSe and GCSE_LTE Motorola Solutions Asks for clarifying the guidance on Public Safety prioritization, to be sent to working groups, based on what TSG RAN has provided last week. OTHER Action Noted This will be taken into account in the prioritisation discussions. This was then noted. Y
5.2 SP-130358 Release 12 Priorities for Public Safety (UK) Home Office Presentation of the U.K. Home Office Release 12 Priorities for Public Safety Discussion Presentation Noted Y
5.2 SP-130363 Rationale for the Public Safety Priorities for Release 12 (UK) Home Office and US Dept of Commerce At TSG SA#61, TSG SA will review SA WG2 progress and make any decisions necessary to ensure successful completion of approved work and study items. To facilitate the prioritisation discussion at TSG SA#61, the [...]. Discussion Discussion Noted Noted. This was provided as further reading for the presentation in SP-130358. Y
5.2 SP-130457 Prioritisation for Direct Discovery in ProSe/D2D Qualcomm Incorporated, China Mobile, China Unicom, Deutsche Telekom, Softbank Mobile, T-Mobile US, Samsung In this paper, we consider to the possibility that a down scoping of the ongoing study in Proximity Services WID in SA WG2 is needed. The supporting companies of this paper would like to point out that is impor [...]. DISCUSSION Discussion Noted Y
5.2 SP-130473 Release 12 ProSe and GCSE_LTE Prioritization Telecom Italia This document highlights the sourcing company preference for Rel-12 ProSe and GCSE_LTE prioritization, based on the feature components of described in SP-130337 DISCUSSION Discussion Noted Y
5.2 SP-130364 Prioritising EPC support of ProSe communication over WLAN Intel, Broadcom, MediaTek, Sony Mobile, ZTE, NEC, InterDigital, III, Radisys, ETRI The present contribution proposes that SA WG2 should prioritise the work on EPC support of ProSe communication over WLAN because the feature has potential for benefitting both operators and end users, has minim [...]. Discussion Discussion Revised SP-130466 Additional supporting companies added and additional modifications in SP-130466 Y
5.2 SP-130466 Prioritising EPC support of ProSe communication over WLAN Intel, Broadcom, MediaTek, Sony Mobile, ZTE, NEC, InterDigital, III, Radisys, ETRI The present contribution proposes that SA WG2 should prioritise the work on EPC support of ProSe communication over WLAN because the feature has potential for benefitting both operators and end users, has minim [...]. DISCUSSION Discussion Noted SP-130364 Y
5.2 SP-130424 UPCON Feature Prioritization Input to TSG SA#61 KDDI, NTT DoCoMo, Orange, AT&T, CMCC, China Telecom, Bell Mobility At TSG SA#61, TSG SA will review SA WG2 progress and make any decisions necessary to ensure success of approved work and study items. This contribution provides operator views on UPCON prioritization. DISCUSSION Discussion Noted Y
5.2 SP-130472 UPCON Feature Prioritization for Rel-12 Huawei, Hisilicon This contribution provides source companies' view on UPCON prioritization to adapt the Rel-12 timeframe DISCUSSION Discussion Noted Y
5.2 SP-130474 UPCON Feature Prioritization Telecom Italia This document highlights the sourcing company preference for Rel-12 UPCON prioritization, based on the feature components described in SP-130337 DISCUSSION Discussion Noted Y
5.2 SP-130419 KPN priority for 3GPP Release 12 KPN Presentation of KPN priority for 3GPP Release 12 DISCUSSION Presentation Noted Y
5.2 SP-130458 Sony's View on ProSe Release-12 Prioritization of SA WG2 at TSG SA#61 Sony Europe Ltd, Sony Mobile Communications Sony's View on ProSe Release-12 Prioritization of SA WG2 DISCUSSION Presentation Noted Y
5.2 SP-130395 SA WG2 work prioritization Samsung Samsung's View of Prioritization of SA WG2 Features at TSG SA#61 DISCUSSION Presentation Noted Y
5.2 SP-130468 Considerations for Release 12 Priorities & the Way forward Orange Summary: The estimated R12 time budgets required for R12 Priority Features/Functions - The 'Big Tree': < 36.5 TR, 18.5 TS - The Smaller Items: < 11.5 TR, 16 TS -IMS: 3.5 TR, 3 TS - The total: < 51.5 TR, 37.5 TS [...]. DISCUSSION Discussion Noted Y
5.2 SP-130460 3GPP Release 12 prioritisation Vodafone, Ericsson This document highlights the sourcing companies' preference for Rel-12 prioritisation. DISCUSSION Discussion Noted Y
5.2 SP-130485 [Draft] SA WG2 Prioritization Output SA WG2 Chairman Summary of Prioritisation contributions and impacts with respect to the SA WG2 time budget. Presentation Discussion Revised SP-130486 Delegates were asked to review the slides for further discussion. Y
5.2 SP-130486 (Updated) SA WG2 Prioritization Output SA WG2 Chairman Summary of Prioritisation contributions and impacts with respect to the SA WG2 time budget. Presentation Discussion Noted SP-130485 Noted. Results of the off-line discussions were provided in SP-130489 and SP-130490. Y
5.2 SP-130500 SA WG2 Prioritization Output SA WG2 Chairman Summary of Prioritisation contributions and impacts with respect to the SA WG2 time budget. Presentation Discussion Revised SP-130503 This was revised to correct the figure in SP-130503 Y
5.2 SP-130503 SA WG2 Prioritization Output SA WG2 Chairman Summary of Prioritisation contributions and impacts with respect to the SA WG2 time budget. Presentation Discussion Revised SP-130506 SP-130500 Y
5.2 SP-130506 SA WG2 Prioritization Output SA WG2 Chairman Summary of Prioritisation contributions and impacts with respect to the SA WG2 time budget. Presentation Discussion Noted and Endorsed SP-130503 Noted and the general work planning for SA WG2 was endorsed. Y
5.2 SP-130487 Way forward for MTCe SDDTE in Rel-12 Alcatel-Lucent, Qualcomm Incorporated, BlackBerry While no formal agreements were reached on not proceeding on with the key issue 'Efficient Small Data Transmission' enhancements under the MTCe TR scope for SDDTE, this paper argues that those solutions with a [...]. DISCUSSION Discussion Noted This was taken into account in the prioritization discussions and was noted. Y
5.2 SP-130489 UPCON Prioritization Output TSG SA Drafting UPCON Prioritization Output DISCUSSION Discussion Noted An LS was drafted to SA WG2 outlining these agreements in SP-130493 and this presentation was noted. Y
5.2 SP-130493 [DRAFT] LS on Prioritisation of User Plane Congestion Management (UPCON) TSG SA To: SA WG2 LS OUT Approval Revised SP-130499 - This was discussed to clarify the text off-line and the LS was revised in SP-130499 Y
5.2 SP-130499 [DRAFT] LS on Prioritisation of User Plane Congestion Management (UPCON) TSG SA To: SA WG2 LS OUT Approval Revised SP-130502 SP-130493 - This was revised to remove draft in SP-130502 Y
5.2 SP-130502 LS on Prioritisation of User Plane Congestion Management (UPCON) TSG SA To: SA WG2 LS OUT Approval Approved SP-130499 - Y
5.2 SP-130490 SA WG2 Prioritization Offline Discussion TSG SA Drafting SA WG2 Prioritization Offline Discussion DISCUSSION Discussion Noted This will be reviewed again at TSG SA#62. Y
5.2 SP-130501 SA WG2 Budget Agreements vs Meeting time SA WG2 Chairman - DISCUSSION Discussion Noted Y
6 - - - - - - - - - - -
7 - - - - - - - - - - -
7.1 - - - - - - - - - - -
7.1 SP-130409 SA WG1 Report to TSG SA#61 SA WG1 Chairman SA WG1 Chairman's Status Report to TSG SA#61 Report Presentation Noted The SA WG1 Chairman was thanked for this report, which was noted. Y
7.2 - - - - - - - - - - -
7.2 SP-130336 TSG SA WG2 Report and Questions for Advice at TSG SA#61 SA WG2 Chairman SA WG2 Chairman's Status Report to TSG SA#61 Report Presentation Revised SP-130471 Revised in SP-130471 Y
7.2 SP-130471 TSG SA WG2 Report and Questions for Advice at TSG SA#61 SA WG2 Chairman SA WG2 Chairman's Status Report to TSG SA#61 Report Presentation Noted SP-130336 The SA WG2 Chairman was thanked for this report, which was noted. Y
7.3 - - - - - - - - - - -
7.3 SP-130396 SA WG3 Status Report SA WG3 Chairman SA WG3 Chairman's Status Report to TSG SA#61 Report Information Noted The SA WG3 Chairman was thanked for this report, which was noted. Y
7.4 - - - - - - - - - - -
7.4 SP-130344 SA WG4 Status Report at TSG SA#61 SA WG4 Chairman SA WG4 Chairman's Status Report to TSG SA#61 Report Presentation Noted The SA WG4 Chairman was thanked for this report, which was noted. Y
7.5 - - - - - - - - - - -
7.5 SP-130426 SA WG5 Status Report SA WG5 Chairman SA WG5 Chairman's Status Report to TSG SA#61 Report Presentation Revised SP-130469 Revised to correct references to NSN in SP-130469 Y
7.5 SP-130469 SA WG5 Status Report SA WG5 Chairman SA WG5 Chairman's Status Report to TSG SA#61 Report Presentation Noted SP-130426 The SA WG5 Chairman was thanked for this report, which was noted. Y
7.6 - - - - - - - - - - -
7.6 SP-130475 TSG RAN Status Report to TSG SA#61 TSG RAN Chairman TSG RAN Chairman's report to TSG SA#61 Report Presentation Revised SP-130494 Revised in SP-130494 Y
7.6 SP-130494 TSG RAN Status Report to TSG SA#61 TSG RAN Chairman TSG RAN Chairman's report to TSG SA#61 Report Presentation Noted SP-130475 The TSG RAN Chairman was thanked for this report, which was noted. Y
7.6 SP-130476 Draft report of TSG RAN meeting #61 TSG RAN Secretary (MCC) Draft meeting report of TSG RAN Meeting #61, for information. Report Information Noted This was provided for information and was noted. Y
7.6 SP-130479 Letter to ITU on Update submission for IMT-2000 CDMA DS and IMT-2000 CDMA TDD toward Rev. 12 of Rec. ITU-R M.1457 TSG RAN ITU-R Working Party 5D (WP 5D) is developing Revision 12 of the Recommendation M.1457 ('Detailed specifications of the terrestrial radio interfaces of IMT-2000 (IMT-2000)'). According to the approved procedure [...]. OTHER Endorsement Version for PCG in SP-130495 Version for PCG in SP-130495 Y
7.6 SP-130495 LS to PCG: Letter to ITU on Update submission for IMT-2000 CDMA DS and IMT-2000 CDMA TDD toward Rev. 12 of Rec. ITU-R M.1457 TSG SA ITU-R Working Party 5D (WP 5D) is developing Revision 12 of the Recommendation M.1457 ('Detailed specifications of the terrestrial radio interfaces of IMT-2000 (IMT-2000)'). According to the approved procedure [...]. LS OUT Approval Approved - Version for PCG in SP-130495 Y
7.6 SP-130480 Letter to ITU on Liaison statement to External Organizations regarding study on future technology trends for terrestrial IMT Systems TSG RAN ITU-R Working Party 5D (WP 5D) has started working on a preliminary draft new Report ITU-R M.[IMT.FUTURE TECHNOLOGY TRENDS] to look at the future technologies for terrestrial IMT systems. It is planned that WP [...]. OTHER Endorsement Version for PCG in SP-130496 Version for PCG in SP-130496 Y
7.6 SP-130496 LS to PCG: Letter to ITU on Liaison statement to External Organizations regarding study on future technology trends for terrestrial IMT Systems TSG SA ITU-R Working Party 5D (WP 5D) has started working on a preliminary draft new Report ITU-R M.[IMT.FUTURE TECHNOLOGY TRENDS] to look at the future technologies for terrestrial IMT systems. It is planned that WP [...]. LS OUT Approval Approved - Version for PCG in SP-130496 Y
7.6 SP-130481 Letter to ITU on Liaison Statement to PPDR External Organizations on the technologies for public protection and disaster relief communications associated with work on WRC-15 agenda item 1.3 TSG RAN ITU-R WP5A sent an LS to 3GPP (see RP-130738 in attachment) indicating that the Group is considering how the evolution in technology has met the requirements of public protection and disaster relief (PPDR) orga [...]. OTHER Endorsement Version for PCG in SP-130497 For forwarding to the PCG Y
7.6 SP-130497 LS to PCG: Letter to ITU on Liaison Statement to PPDR External Organizations on the technologies for public protection and disaster relief communications associated with work on WRC-15 agenda item 1.3 TSG SA ITU-R WP5A sent an LS to 3GPP (see RP-130738 in attachment) indicating that the Group is considering how the evolution in technology has met the requirements of public protection and disaster relief (PPDR) orga [...]. LS OUT Approval Approved - Y
7.6 SP-130482 Letter to ITU in answer to Liaison statement to external organizations on Study on IMT Vision for 2020 and Beyond TSG RAN ITU-R Working Party 5D (WP 5D) is developing a new Recommendation ITU-R M.[IMT.VISION] ' Framework and overall objectives of the future development of IMT for 2020 and beyond' . This Recommendation will help en [...]. OTHER Endorsement Version for PCG in SP-130498 For forwarding to the PCG Y
7.6 SP-130498 LS to PCG: Letter to ITU in answer to Liaison statement to external organizations on Study on IMT Vision for 2020 and Beyond TSG SA ITU-R Working Party 5D (WP 5D) is developing a new Recommendation ITU-R M.[IMT.VISION] ' Framework and overall objectives of the future development of IMT for 2020 and beyond' . This Recommendation will help en [...]. LS OUT Approval Approved - Y
7.7 - - - - - - - - - - -
7.7 SP-130461 TSG CT Status report TSG CT Chairman TSG CT Chairman's report to TSG SA#61 Report Presentation Noted The TSG CT Chairman was thanked for this report, which was noted. Y
7.7 SP-130462 TSG CT draft meeting report TSG CT Secretary (MCC) Draft meeting report of TSG CT Meeting #61, for information. Report Information Noted This was provided for information and was noted. Y
7.7 SP-130463 IETF status report TSG CT Chairman Status of IETF dependencies Report Presentation Noted The TSG CT Chairman was thanked for this report, which was noted. Y
7.8 - - - - - - - - - - -
7.8 SP-130425 TSG GERAN Status Report to TSG SA#61 TSG GERAN Chairman TSG GERAN Status Report to TSG SA#61 Report Presentation Noted The TSG GERAN Chairman was thanked for this report, which was noted. Y
8 - - - - - - - - - - -
8.1 - - - - - - - - - - -
8.2 - - - - - - - - - - -
8.3 - - - - - - - - - - -
8.4 - - - - - - - - - - -
8.4 SP-130367 5 CRs to 23.167 (EMC1; Rel-7, Rel-8, Rel-9, Rel-10, Rel-11) SA WG2 23.167 CR0228R2; 23.167 CR0229R2; 23.167 CR0230R2; 23.167 CR0231R2; 23.167 CR0232R2 CR Pack Approval Approved Y
8.5 - - - - - - - - - - -
8.5 SP-130411 Stage 1 CRs on TEI8 (on Removal of IMS Operator Determined Barring Outgoing Premium Rate requirements) SA WG1 22.041 CR0021; 22.041 CR0020; 22.041 CR0019; 22.041 CR0018R1 CR Pack Approval Approved Y
8.5 SP-130431 Rel-8 CRs on OAM Maintenance and small Enhancements (OAM8) SA WG5 32.712 CR0004; 32.712 CR0005; 32.712 CR0006; 32.712 CR0007 CR Pack Approval Approved Y
9 - - - - - - - - - - -
9 SP-130368 3 CRs to 23.272 (TEI9, SAES-CSFB; Rel-9, Rel-10, Rel-11) SA WG2 23.272 CR0890R2; 23.272 CR0891R1; 23.272 CR0892R1 CR Pack Approval Approved Y
9 SP-130369 4 CRs to 23.203 (EHNB; Rel-9, Rel-10, Rel-11, Rel-12) SA WG2 23.203 CR0836R1; 23.203 CR0837R2; 23.203 CR0838R1; 23.203 CR0839R1 CR Pack Approval Approved NOTE: The Rel-12 CR is not a mirror CR but is on the same subject and is presented with the Rel-9 CR Y
9 SP-130345 CRs to TS 26.237 on 'Corrections on SDP Attributes (IMS_PSS_MBMS_US_EXT)' (Release 9 to Release 11) SA WG4 26.237 CR0075R1; 26.237 CR0076R1; 26.237 CR0077R1 CR Pack Approval Approved Y
9 SP-130346 CRs to TS 26.346 on 'Essential Correction to Schedule Fragment MIME Type (PMA-MBS_Ext)' (Release 9 to Release 11) SA WG4 26.346 CR0328; 26.346 CR0329; 26.346 CR0330 CR Pack Approval Approved Y
9 SP-130437 Rel-9 CRs on Multimedia Telephony (MMTel) Service and Supplementary Services - Online Charging and completion for Offline Charging(eMMTel-SS-CH) SA WG5 32.275 CR0045; 32.275 CR0046; 32.275 CR0047 CR Pack Approval Approved Y
9 SP-130438 Rel-9 CRs on Support of Real-time Transfer of Tariff Information (RTTI) in IMS charging (IMSTSS-RTTI-CH) SA WG5 32.260 CR0218; 32.260 CR0219; 32.260 CR0220; 32.260 CR0221 CR Pack Approval Approved Y
9 SP-130439 Rel-9 CRs on SON self-optimization managemen (LTE_SON-OAM) SA WG5 32.522 CR0140; 32.522 CR0141; 32.522 CR0142R1; 32.523 CR0003R1 CR Pack Approval Approved Y
10 - - - - - - - - - - -
10 SP-130347 CR to TS 26.247 on 'Corrections to DASH (HTTP_SDS)' (Release 10) SA WG4 26.247 CR0036 CR Pack Approval Approved Y
10 SP-130348 CRs to TS 26.346 on 'Essential Corrections of DASH over MBMS (MBS_Enh)' (Release 10 and Release 11) SA WG4 26.346 CR0331R3; 26.346 CR0332R1 CR Pack Approval Approved Y
10 SP-130432 Rel-10 CRs on OAM Maintenance and small Enhancements (OAM10) SA WG5 32.423 CR0074R2; 32.423 CR0075R2; 32.526 CR0034; 32.626 CR0005 CR Pack Approval Approved Y
10 SP-130434 Rel-10 CR on Charging Management (CH10) SA WG5 32.251 CR0286R1 CR Pack Approval Approved Y
10 SP-130440 Rel-10 CRs on SON Self-optimization management continuation (LTE-SON-OAM_SO) SA WG5 32.526 CR0031R1; 32.526 CR0032R1 CR Pack Approval Approved Y
11 - - - - - - - - - - -
11.1 - - - - - - - - - - -
11.2 - - - - - - - - - - -
11.3 - - - - - - - - - - -
11.4 - - - - - - - - - - -
11.4 SP-130370 3 CRs to 23.204, 23.272 (SIMTC; Rel-11, Rel-12) SA WG2 23.204 CR0102R1; 23.204 CR0103R1; 23.272 CR0881R1 CR Pack Approval Approved Y
11.4 SP-130403 Release 11 CRs on Reachability Aspects of SIMTC (SIMTC-Reach) SA WG3 23.682 CR0075R1 CR Pack Approval Approved Y
11.4 SP-130405 Release 11 CRs on System Improvements to Machine-Type Communications(SIMTC) SA WG3 WITHDRAWN CR Pack Approval Withdrawn WITHDRAWN N
11.5 - - - - - - - - - - -
11.6 - - - - - - - - - - -
11.6 SP-130371 2 CRs to 23.228 (eMPS; Rel-11, Rel-12) SA WG2 23.228 CR1041R2; 23.228 CR1042R2 CR Pack Approval Approved Y
11.7 - - - - - - - - - - -
11.8 - - - - - - - - - - -
11.8 SP-130372 2 CRs to 23.401 (NWK-PL2IMS; Rel-11, Rel-12) SA WG2 23.401 CR2581R2; 23.401 CR2582R2 CR Pack Approval Approved Y
11.9 - - - - - - - - - - -
11.10 - - - - - - - - - - -
11.10 SP-130373 2 CRs to 23.203 (SAPP; Rel-11, Rel-12) SA WG2 23.203 CR0834R1; 23.203 CR0835R1 CR Pack Approval Approved Y
11.11 - - - - - - - - - - -
11.12 - - - - - - - - - - -
11.13 - - - - - - - - - - -
11.14 - - - - - - - - - - -
11.15 - - - - - - - - - - -
11.16 - - - - - - - - - - -
11.17 - - - - - - - - - - -
11.18 - - - - - - - - - - -
11.19 - - - - - - - - - - -
11.20 - - - - - - - - - - -
11.21 - - - - - - - - - - -
11.22 - - - - - - - - - - -
11.23 - - - - - - - - - - -
11.24 - - - - - - - - - - -
11.25 - - - - - - - - - - -
11.26 - - - - - - - - - - -
11.27 - - - - - - - - - - -
11.28 - - - - - - - - - - -
11.28 SP-130349 CR to TS 26.346 on 'Correction to Reception Reporting Aggregation postReceptionReport timer calculation (EMM-DDE)' (Release 11) SA WG4 26.346 CR0327 CR Pack Approval Approved Y
11.29 - - - - - - - - - - -
11.29 SP-130350 CR to TS 26.247 on 'Corrections to DASH (M3DV)' (Release 11) SA WG4 26.247 CR0037 CR Pack Approval Approved Y
11.30 - - - - - - - - - - -
11.31 - - - - - - - - - - -
11.32 - - - - - - - - - - -
11.32 SP-130443 Rel-11 CRs on Unification of Charging session from SIP AS and SRVCC functions in IMS (UCHIMS_AS-SRVCC) SA WG5 32.260 CR0213; 32.260 CR0214; 32.299 CR0536; 32.299 CR0537 CR Pack Approval Approved Y
11.32 SP-130464 Rel-11 CR on Charging Management (CH11) SA WG5 32.275 CR0044R1 CR Pack Approval Approved Y
11.33 - - - - - - - - - - -
11.33 SP-130433 Rel-11 CRs on OAM Maintenance and small Enhancements (OAM11) SA WG5 28.103 CR0005R1; 28.652 CR0002R1; 28.653 CR0002R1; 28.661 CR0001R3; 28.662 CR0001R3; 28.663 CR0001R1; 28.732 CR0001R1; 32.102 CR0050R1; 32.157 CR0002R1; 32.526 CR0033; 32.526 CR0035; 32.626 CR0006; 32.766 CR005 [...]. CR Pack Approval Approved Y
11.33 SP-130441 Rel-11 CRs on IRP framework enhancements to support Management of Converged Networks(OAM-FMC-IRP) SA WG5 28.628 CR0005; 28.629 CR0003R1 CR Pack Approval Approved Y
11.34 - - - - - - - - - - -
11.35 - - - - - - - - - - -
11.35 SP-130410 Stage 1 CR on TEI11 (on SMSC Usage Restriction in Roaming) SA WG1 22.088 CR0006R2 CR Pack Approval Noted This was noted and the revision in SP-130456 was approved. Y
11.35 SP-130420 Stage 1 CR on TEI11 (on SMSC Usage Restriction in Roaming) Orange 22.088 CR0006R3 CR Pack Approval Revised SP-130456 Proposed update to SP-130410. Y
11.35 SP-130456 Stage 1 CRs on TEI11 (on SMSC Usage Restriction in Roaming) Orange, Telefonica, Telecom Italia, Vodafone 22.088 CR0006R4 CR Pack Approval Approved SP-130420 Proposed update to SP-130410. Y
11.35 SP-130374 4 CRs to 23.060, 23.401 (TEI11; Rel-11, Rel-12) SA WG2 23.060 CR1803R2; 23.060 CR1802R2; 23.401 CR2570R2; 23.401 CR2569R2 CR Pack Approval Approved Y
11.35 SP-130375 4 CRs to 23.401 (TEI11, SAES; Rel-11, Rel-12) SA WG2 23.401 CR2493R3; 23.401 CR2528R2; 23.401 CR2575R1; 23.401 CR2576R1 CR Pack Approval Approved Y
11.35 SP-130376 5 CRs to 23.167, 23.272 (TEI11, EMC1, SAES-CSFB; Rel-11) SA WG2 23.167 CR0234R1; 23.272 CR0882R1; 23.272 CR0883R2; 23.272 CR0889R2; 23.272 CR0893R2 CR Pack Approval Approved Y
11.35 SP-130377 1 CR to 23.272 (TEI11, SAES-CSFB; Rel-11) SA WG2 23.272 CR0880R2 CR Pack Approval Noted This was noted and the revision in SP-130362 was approved. Y
11.35 SP-130362 Revision of SA WG2 agreed CR: 23.272 CR0880R3 (TEI11) NSN, NEC Update to SA WG2 agreed CR 23.272 CR0880R3 in SP-130377 CR Pack Approval Approved Y
11.35 SP-130378 4 CRs to 23.237, 23.401 (TEI11, IMS_EMER_GPRS_EPS-SRVCC, SIPTO; Rel-11, Rel-12) SA WG2 23.237 CR0466R2; 23.237 CR0467R1; 23.401 CR2583R1; 23.401 CR2584R2 CR Pack Approval Approved Y
11.35 SP-130351 CRs to TS 26.114 on 'Correction of DTMF handling (TEI11)' (Release 11 and Release 12) SA WG4 26.114 CR0258; 26.114 CR0259 CR Pack Approval Approved Y
11.35 SP-130444 Rel-11 CR on TEI (TEI11) SA WG5 WITHDRAWN CR Pack Approval Withdrawn WITHDRAWN N
11.36 - - - - - - - - - - -
12 - - - - - - - - - - -
12 SP-130343 LS from SA WG2: LS Reply on LTE-HRPD SON WID conditional approval SA WG2 SA WG2 would like to thank RAN for the LS in S2-132356/RP-130865 and the information given. SA WG2 discussed the conclusion of TR 37.813 on LTE-HRPD (High Rate Packet Data in 3GPP2) Inter-RAT SON, and the foll [...]. LS In Information Noted S2-133082 Y
12 SP-130421 LS from RAN WG3: LS Reply on LTE-HRPD SON WID conditional approval RAN WG3 RAN WG3 would like to thank SA WG2 for the LS on LTE-HRPD SON WID conditional approval. RAN WG3 has reviewed the proposed changes by SA WG2 and would like to confirm that this is in line with RAN WG3 agreements [...]. LS In Information Noted R3-131611 Y
12 SP-130422 Submission to SA#61 of a technically endorsed CR at SA WG2#98 Alcatel-Lucent, Alcatel-Lucent Shanghai, Huawei, Hisilicon, China Telecom, Bell, ZTE, Qualcomm Incorporated, Ericsson SA WG2#98 has technically endorsed CR to 23.402 in S2-132960 introducing the description of the S121 interface for Inter-RAT SON between LTE and HRPD. This CR was not agreed but it was technically endorsed due [...]. DISCUSSION Information Noted This was provided as background to the proposed CR in SP-130423 and was noted. Y
12 SP-130423 23.402 CR1162R2: Add Interface Description of E-UTRAN-HRPD Inter-RAT SON - technically endorsed at SA WG2#98 Alcatel-Lucent, Alcatel-Lucent Shanghai, Huawei, Hisilicon, China Telecom, Bell, ZTE, Qualcomm Incorporated, Ericsson 23.402 CR1162R2 CR Pack Approval Approved Y
12.1 - - - - - - - - - - -
12.2 - - - - - - - - - - -
12.2 SP-130398 Revised WID for Web Real Time Communication (WebRTC) Access to IMS SA WG3 Objective: SA WG1 objectives: The objective of this work item is to specify service requirements for: - the ability for WebRTC clients to access IMS, including for example, reusing IMS client security credentia [...]. WID Approval Noted This was noted and the revision in SP-130484 was approved. Y
12.2 SP-130459 Revision of SA WG3 objectives in WebRTC WID Alcatel-Lucent, Orange, Huawei, ZTE SA WG3 has approved the SA WG3 objectives for the IMS_WebRTC WID in S3-130837, which is being contributed to SA under separate cover for endorsement. The objective related to authentication appears to disallow [...]. WID Approval Revised SP-130484 Proposed update to SP-130398 Y
12.2 SP-130484 Revision of SA WG3 objectives in WebRTC WID Alcatel-Lucent, Orange, Huawei, ZTE SA WG3 has approved the SA WG3 objectives for the IMS_WebRTC WID in S3-130837, which is being contributed to SA under separate cover for endorsement. The objective related to authentication appears to disallow [...]. WID Approval Approved SP-130459 Proposed update to SP-130398 Y
12.3 - - - - - - - - - - -
12.4 - - - - - - - - - - -
12.5 - - - - - - - - - - -
12.6 - - - - - - - - - - -
12.7 - - - - - - - - - - -
12.8 - - - - - - - - - - -
12.9 - - - - - - - - - - -
12.10 - - - - - - - - - - -
12.11 - - - - - - - - - - -
12.12 - - - - - - - - - - -
12.13 - - - - - - - - - - -
12.13 SP-130413 Stage 1 CRs on RAN Sharing Enhancements (RSE) SA WG1 22.101 CR0463R1 CR Pack Approval Approved Y
12.14 - - - - - - - - - - -
12.15 - - - - - - - - - - -
12.15 SP-130412 Stage 1 CRs on Proximity-based Services (ProSE) SA WG1 22.115 CR0071; 22.278 CR0186; 22.278 CR0187R1; 22.278 CR0188R1; 22.278 CR0189R1 CR Pack Approval Approved Y
12.16 - - - - - - - - - - -
12.16 SP-130397 Revised WID for Group Communication System Enablers for LTE (GCSE_LTE) including security SA WG3 Objective: The SA WG1 objective is to specify the system enablers' Stage 1 service requirements to the 3GPP system to support group communication over LTE for critical communications such as Public Safety. The [...]. WID Approval Approved Y
12.17 - - - - - - - - - - -
12.18 - - - - - - - - - - -
12.19 - - - - - - - - - - -
12.20 - - - - - - - - - - -
12.20 SP-130379 5 CRs to 23.060, 23.401 (LIMONET; Rel-12) SA WG2 23.060 CR1805R1; 23.060 CR1807R2; 23.401 CR2574R2; 23.401 CR2585R1; 23.401 CR2587R1 CR Pack Approval Approved Y
12.20 SP-130380 1 CR to 23.401 (LIMONET; Rel-12) SA WG2 23.401 CR2586R1 CR Pack Approval Noted BlackBerry commented that problems had been discovered after SA WG2 approval of this CR and suggested returning it to SA WG2 for further consideration. This CR was then noted. Y
12.21 - - - - - - - - - - -
12.21 SP-130381 1 CR to 23.402 (OPIIS; Rel-12) SA WG2 23.402 CR1166R1 CR Pack Approval Approved Y
12.22 - - - - - - - - - - -
12.22 SP-130382 5 CRs to 23.203 (P4C-F; Rel-12) SA WG2 23.203 CR0826R2; 23.203 CR0830R1; 23.203 CR0831R2; 23.203 CR0832R2; 23.203 CR0833R1 CR Pack Approval Approved Y
12.22 SP-130386 TR 23.896, version 1.3.1: Technical Report on Support for fixed broadband access network convergence; Stage-2 (Release 12) SA WG2 Abstract of document: TR 23.896 describes solutions for the Evolved Packet System (EPS) to facilitate policy and charging control in the fixed broadband access network in the convergent scenario where a single [...]. TR Information Noted Noted. SA WG2 were asked to check the use of specific versions for external references Y
12.22 SP-130442 Rel-12 CRs on Policy and Charging Enforcement Function (PCEF) based Charging for traffic from fixed terminals and NSWO traffic from 3GPP UEs in fixed broadband access networks (P4C-F-CH_P) SA WG5 32.240 CR0368R1; 32.251 CR0288R1; 32.251 CR0289R1; 32.251 CR0290R1 CR Pack Approval Approved Y
12.23 - - - - - - - - - - -
12.24 - - - - - - - - - - -
12.24 SP-130361 Standardization of Machine-type Communications MCC Work Plan Manager Standardization of Machine-type Communications (2013-06) is available at : ftp://www.3gpp.org/Information/WORK_PLAN/Description_Releases/M2M_20130630.zip OTHER Information Noted This was provided for information and was noted. Y
12.25 - - - - - - - - - - -
12.25 SP-130338 LS from GSMA and WBA: Wi-Fi Roaming Task Force - Signalling Optimisation GSMA and WBA The Task Force concluded that one approach to control WLAN authentication signalling is for the operator to be able to set the aggressiveness of the authentication/association attempts of the UE to operator con [...]. LS In Information Noted LS 3GPP WFA 26062013 Y
12.25 SP-130339 LS from WBA: WBA Carrier Wi-Fi Liaison Statement WBA The main objective of the WBA project on Carrier Wi-Fi is to create a definition on Carrier Wi-Fi and identify the key components that should be in place in order that operators can have a clear path to develop [...]. LS In Action Response in SP-130504 LS_to_3GPP_31072013 Response drafted in SP-130491. Final response in SP-130504 Y
12.25 SP-130477 LS from TSG RAN: Reply LS on WBA Carrier Wi-Fi Liaison Statement TSG RAN 3GPP would like to thank WBA for the LS on WBA Carrier Wi-Fi Liaison Statement. 3GPP RAN has not been using so far the term carrier grade in its work with relation to WLAN technology and has no definition for [...]. LS In Information Noted RP-131367 A response LS to WBA was drafted in SP-130491. This LS was then noted. Y
12.25 SP-130491 Reply LS on WBA Carrier Wi-Fi Liaison Statement TSG SA To: WBA. CC: SA WG1 LS OUT Approval Revised SP-130504 - Response to SP-130399 Y
12.25 SP-130504 Reply LS on WBA Carrier Wi-Fi Liaison Statement TSG SA To: WBA. CC: SA WG1 LS OUT Approval Approved SP-130491 - Y
12.25 SP-130387 TR 23.865: 'Study on WLAN network selection for 3GPP terminals; Stage 2' for approval SA WG2 Abstract of document: TR 23.865 describes enhancements to solutions for WLAN network selection. These include enhancements to ANDSF framework and 3GPP WLAN network selection procedures based on Hotspot 2.0 spec [...]. TR Approval Approved This TR was approved and placed under TSG SA change control (Release 12). Y
12.25 SP-130467 Missing policies for ANDSF for WLAN network selection and traffic steering Vodafone This document proposes to add a WLAN percentage radio signal strength policy to the proposed Release 12 WLANSP ANDSF node and a minimum throughput policy in ANDSF ISMP node as part of the WLAN_NS work in Releas [...]. DISCUSSION Discussion Noted Noted. It was agreed that the overall time situation will be reviewed to determine whether there is time to consider these items in the normative work. Y
12.25 SP-130342 LS from SA WG2: Reply LS on WiFi-Alliance Offloading Standards Work SA WG2 SA WG2 thanks Wi-Fi alliance for sharing its understanding and assessment of the differences on the scope of 3GPP and Wi-Fi Alliance Hotspot 2.0 programs. SA WG2 has discussed these assessments, and provides th [...]. LS In Information Noted S2-133081 Y
12.26 - - - - - - - - - - -
12.27 - - - - - - - - - - -
12.27 SP-130383 1 CR to 23.203 (ABC; Rel-12) SA WG2 23.203 CR0823R2 CR Pack Approval Approved Y
12.27 SP-130436 Rel-12 CRs on Charging for Application Based Charging (ABC) SA WG5 32.240 CR0367R1; 32.251 CR0280R1; 32.251 CR0281R1; 32.251 CR0282R1; 32.251 CR0283R1; 32.251 CR0291; 32.296 CR0032R1 CR Pack Approval Approved Y
12.28 - - - - - - - - - - -
12.29 - - - - - - - - - - -
12.29 SP-130406 Release 12 CRs for IMS media plane security extensions (eMEDIASEC) SA WG3 33.328 CR0054R1; 33.328 CR0055R1 CR Pack Approval Approved Y
12.30 - - - - - - - - - - -
12.31 - - - - - - - - - - -
12.32 - - - - - - - - - - -
12.33 - - - - - - - - - - -
12.33 SP-130404 Release 12 CRs on Tunnelling of UE Services over Restrictive Access Networks (Stage 2/3) (TURAN) SA WG3 33.203 CR0199R1; 33.203 CR0201R1; 33.203 CR0202 CR Pack Approval Approved Y
12.34 - - - - - - - - - - -
12.34 SP-130352 CRs to TS 26.114 and TS 26.244 on 'Co-ordination of Video Orientation (CVO)' (Release 12) SA WG4 26.114 CR0257R2; 26.114 CR0260; 26.244 CR0050 CR Pack Approval Approved Y
12.35 - - - - - - - - - - -
12.36 - - - - - - - - - - -
12.36 SP-130353 CRs to TS 26.237 on 'IMS-based Streaming and Download Delivery Enhancements (IMS_SDE)' (Release 12) SA WG4 26.237 CR0079R1; 26.237 CR0080 CR Pack Approval Approved Y
12.37 - - - - - - - - - - -
12.37 SP-130354 CRs to TS 26.245, TS 26.247 and TS 26.430 on 'Mobile stereoscopic 3D services extensions (M3DV_Ext)' (Release 12) SA WG4 26.245 CR0003R1; 26.247 CR0035; 26.430 CR0002R1 CR Pack Approval Approved Y
12.38 - - - - - - - - - - -
12.39 - - - - - - - - - - -
12.40 - - - - - - - - - - -
12.40 SP-130341 LS from CT WG4: Reply LS on End-to-end QoS handling of MTSI CT WG4 Regarding the new requirements being raised by SA WG4 on End-to-end QoS handling of MTSI, CT WG4 kindly informs SA WG4 that some concerns were expressed by CT WG4 on the wide system impacts this work may imply [...]. LS In Information Noted C4-131520 Noted. SA WG4 were encouraged to fulfil the actions raised in this LS Y
12.40 SP-130355 CR to TS 26.114 on 'Procedures for selecting the media sending rate (E2EMTSI)' (Release 12) SA WG4 26.114 CR0255R1 CR Pack Approval Approved Y
12.41 - - - - - - - - - - -
12.41 SP-130400 Revised WID for Lawful Interception Rel-12 (LI12) SA WG3 Objective: The objective of this work item is to update lawful interception specifications for the latest Rel-12 architecture and services as described in the above justification. The enhancements to specificat [...]. WID Approval Approved Y
12.41 SP-130401 Release 12 CRs on Lawful Interception (LI12) SA WG3 33.106 CR0129; 33.107 CR0128; 33.107 CR0129; 33.107 CR0130; 33.108 CR0212; 33.108 CR0213 CR Pack Approval Approved Y
12.42 - - - - - - - - - - -
12.42 SP-130435 Rel-12 CRs on Charging Management (CH12) SA WG5 32.251 CR0287; 32.260 CR0224R1; 32.295 CR0007R1; 32.296 CR0030R1; 32.296 CR0031R1; 32.298 CR0404R1; 32.298 CR0405; 32.299 CR0532R1; 32.299 CR0533R1; 32.299 CR0539; 32.299 CR0540 CR Pack Approval Approved Y
12.43 - - - - - - - - - - -
12.43 SP-130465 Rel-12 CR on Multi-vendor Plug and Play eNB connection to the network(SON-NM-MUPPET) SA WG5 32.501 CR0006 CR Pack Approval Approved Y
12.43 SP-130445 TS 28.601: Telecommunication management; Core Network (CN) and non-3GPP access Interworking System Network Resource Model (NRM); Integration Reference Point (IRP); Requirements SA WG5 Abstract of document: The document describes the NRM IRP requirements for Core Network (CN) and non-3GPP access Interworking System Network Resource Model (NRM) Changes since last presentation to TSG SA Meeting [...]. TS Information Noted Y
12.43 SP-130446 TS 28.602: Telecommunication management; Core Network (CN) and non-3GPP access Interworking System Network Resource Model (NRM); Integration Reference Point (IRP); Information Service (IS) SA WG5 Abstract of document: The document describes an Integration Reference Point (IRP) named as 'Core Network (CN) and non-3GPP access Interworking System Network Resource Model IRP' Changes since last presentation [...]. TS Information Noted Y
12.43 SP-130447 TS 28.606: Telecommunication management; Core Network (CN) and non-3GPP access Interworking System Network Resource Model (NRM); Integration Reference Point (IRP); Solution Set (SS) definitions SA WG5 Abstract of document: The document describes the solution set for 'Core Network (CN) and non-3GPP access Interworking System Network Resource Model IRP' Changes since last presentation to TSG SA Meeting #57: Th [...]. TS Information Noted Y
12.43 SP-130448 TS 28.611: Telecommunication management; Evolved Packet Core (EPC) and non-3GPP access Interworking System Network Resource Model (NRM); Integration Reference Point (IRP); Requirements SA WG5 Abstract of document: The document describes the NRM IRP requirements for Evolved Packet Core (EPC) and non-3GPP access Interworking System Network Resource Model (NRM) Changes since last presentation to TSG SA [...]. TS Information Noted Y
12.43 SP-130449 TS 28.612: Telecommunication management; Evolved Packet Core (EPC) and non-3GPP access Interworking System Network Resource Model (NRM); Integration Reference Point (IRP); Information Service (IS) SA WG5 Abstract of document: The document describes an Integration Reference Point (IRP) named as 'Evolved Packet Core (EPC) and non-3GPP access Interworking System Network resource Model IRP' Changes since last prese [...]. TS Information Noted Y
12.43 SP-130450 TS 28.616: Telecommunication management; Evolved Packet Core (EPC) and non-3GPP access Interworking System Network Resource Model (NRM); Integration Reference Point (IRP); Solution Set (SS) definitions SA WG5 Abstract of document: The document describes the solution set for 'Evolved Packet Core (EPC) and non-3GPP access Interworking System Network resource Model IRP' Changes since last presentation to TSG SA Meeting [...]. TS Information Noted Y
12.43 SP-130451 TR 32.836: Study on NM Centralized Coverage and Capacity Optimization (CCO) SON Function SA WG5 Abstract of document: An NM centralized CCO function would help operators in reducing OPEX related to the maintenance and optimization of network coverage and capacity by automating these functions. An NM centr [...]. TR Information Noted Y
12.43 SP-130452 TS 32.508: Technical Specification Group Services and System Aspects;Telecommunication Management; Procedure Flows for Multi-Vendor Plug and Play eNB connection to the Network SA WG5 Abstract of document: The present document describes the procedure flows between network entities involved in the Multi-Vendor Plug and Play eNB connection to network. These procedures are based on requirements [...]. TS Information Noted Y
12.43 SP-130453 TR 32.841: Study on WLAN Management SA WG5 Abstract of document: This document describes the study on WLAN management that focuses on WLAN performance monitoring and alarm reporting. Changes since last presentation: First presentation Outstanding Issues [...]. TR Information Noted Y
12.44 - - - - - - - - - - -
12.44 SP-130402 Release 12 CRs on Security small Enhancements (SEC12) SA WG3 33.203 CR0200 CR Pack Approval Approved Y
12.44 SP-130407 Release 12 CRs on TEI (TEI12) SA WG3 33.320 CR0094R3; 33.401 CR0522R1; 33.402 CR0114R1 CR Pack Approval Approved Y
12.45 - - - - - - - - - - -
12.45 SP-130384 4 CRs to 23.060, 23.401 (TEI12; Rel-12) SA WG2 23.060 CR1804R2; 23.060 CR1806R1; 23.401 CR2567R2; 23.401 CR2571R2 CR Pack Approval Approved Y
12.45 SP-130356 CR to TS 26.237 on 'Missing IANA Registration Information and Corrections on SDP Attributes (TEI12)' (Release 12) SA WG4 26.237 CR0078R2 CR Pack Approval Approved Y
13 - - - - - - - - - - -
13.1 - - - - - - - - - - -
13.2 - - - - - - - - - - -
13.3 - - - - - - - - - - -
13.4 - - - - - - - - - - -
13.5. - - - - - - - - - - -
13.6 - - - - - - - - - - -
13.6 SP-130390 New WID on User Location Information reporting improvements SA WG2 Objective: The objective is to provide normative specification of ULI signalling optimizations according to conclusions of the FS_CNO TR 23.843. WID Approval Noted Noted. It is assumed the study work will continue and it is understood that the normative work is already budgeted into the SA WG2 work Y
13.7 - - - - - - - - - - -
13.7 SP-130340 LS from ETSI TC EE: Update on the liaison to 3GPP on Cooperation for Energy Efficiency Measurements ETSI TC EE Dear all, following the liaison from SA WG5 on 'Cooperation for Energy Efficiency Measurements' (reference: S2-122600) and the joint meeting held in Sophia Antipolis on May 29, 2013 a constant update on the ac [...]. LS In Information Noted EE(13)000021 Y
13.8 - - - - - - - - - - -
13.8 SP-130388 TR 23.852: 'Study on S2a Mobility based On GTP and WLAN access to EPC (SaMOG); Stage 2' for approval SA WG2 Abstract of document: TR 23.852 describes solutions to support Trusted WLAN Access with S2a. An S2a option based on GTP and PMIP is described as well as solutions to support S2a based mobility between 3GPP acce [...]. TR Approval Approved Y
13.8 SP-130391 New WID on S2a Mobility Based on Trusted WLAN access to EPC SA WG2 Objective: This work item is intended to specify, in stage 2 normative description, the solution recommended in TR 23.852 clause 9.2 'Conclusions on SaMOG phase 2' for both GTP and PMIP-based S2a. WID Approval Approved Y
13.9 - - - - - - - - - - -
13.9 SP-130389 TR 23.890: 'Optimized Offloading to WLAN in 3GPP-RAT mobility' for information and approval SA WG2 Abstract of document: TR 23.890 describes solutions for optimised offloading to WLAN during 3GPP RAT mobility (FS_WORM). The TR includes one solution which describes some normative enhancements to ANDSF as well [...]. TR Approval Approved Y
13.9 SP-130392 Feature WID for optimized offloading to WLAN in 3GPP RAT mobility SA WG2 Objective: Complete the following changes to technical specifications (where key issues and solutions are as described in TR 23.890): - Solution 1 (Key issue 1): TR 23.890 clause 6.1 o Normative description of [...]. WID Approval Approved Y
13.9 SP-130385 3 CRs to 23.272, 23.401, 23.402 (WORM; Rel-12) SA WG2 23.272 CR0885R2; 23.401 CR2578R2; 23.402 CR1170R1 CR Pack Approval Approved Approved. NOTE: The WORM Work Item is for approval in SP-130392 and these CRs will be presented after the WI Y
13.10 - - - - - - - - - - -
13.11 - - - - - - - - - - -
13.12 - - - - - - - - - - -
13.12 SP-130415 Revised WID on Study on Application specific Congestion control for Data Communication (FS_ACDC) SA WG1 Objective: The objective of this study item is to investigate the following aspects: ? Identify the use cases and potential requirements to allow/restrict the communication initiation of particular applications [...]. WID Approval Approved It was commented that Research in Motion should be BlackBerry. This can be corrected in the Work Plan Y
13.13 - - - - - - - - - - -
13.14 - - - - - - - - - - -
13.15 - - - - - - - - - - -
13.16 - - - - - - - - - - -
13.16 SP-130454 TR 32.851: Study on OAM aspects of Network Sharing SA WG5 Abstract of document: This document is aimed at studying the operational use cases and OAM implications of Network Sharing. The conclusion of the study is to create new TS 32.xxx will be created to capture stag [...]. TR Approval Approved SA WG5 were asked to bring a CR to remove 'hanging paragraphs' at the next meeting. Y
13.17 - - - - - - - - - - -
13.18 - - - - - - - - - - -
13.19 - - - - - - - - - - -
13.19 SP-130455 TR 32.859: Study on Alarm Management SA WG5 Abstract of document: The massive amount of network elements in a mobile system and the variety of network elements and infrastructure equipment creates huge amount of alarms saturating operators alarm manageme [...]. TR Approval Approved SA WG5 were asked to bring a CR to remove 'hanging paragraphs' at the next meeting. Y
14 - - - - - - - - - - -
14 SP-130414 New WID on Service Exposure and Enablement Support (SEES) SA WG1 Objective: Stage 1 objectives: Study and specify service requirements for the support of exposing selected 3GPP functions to - M2M service enablement layers (e.g. ETSI TC M2M and oneM2M). Use cases of oneM2M [...]. WID Approval Revised SP-130492 This WID was revised off-line in SP-130492 Y
14 SP-130492 New WID on Service Exposure and Enablement Support (SEES) SA WG1 Objective: Stage 1 objectives: Study and specify service requirements for the support of exposing selected 3GPP functions to - M2M service enablement layers (e.g. ETSI TC M2M and oneM2M). Use cases of oneM2M [...]. WID Approval Revised SP-130505 SP-130414 Revised in SP-130505 Y
14 SP-130505 New WID on Service Exposure and Enablement Support (SEES) SA WG1 Objective: Stage 1 objectives: Study and specify service requirements for the support of exposing selected 3GPP functions to - M2M service enablement layers (e.g. ETSI TC M2M and oneM2M). Use cases of oneM2M [...]. WID Approval Approved SP-130492 Y
14 SP-130393 New WID on Network Provided Location Information for IMS (TWAN case) SA WG2 Objective: The intention of this work item is to extend the architecture defined as part of NWK-PL2IMS to allow support of TWAN connected to EPC as IPCAN, to make the TWAN location (cell-Id, e.g. fixed-line id [...]. WID Approval Approved Y
14 SP-130427 New WID Charging per IP Connectivity Access Network (IP-CAN) Session (CHIPS) SA WG5 Objective: This feature provides an IP-CAN session level charging context for both on-line and off-line charging over the Gy and Gz reference points in order to achieve the following benefits: 1. There is one [...]. WID Approval Approved Y
14 SP-130428 New WID Charging using an Alternative Roaming Provider (CHARP) SA WG5 Objective: To support the EU roaming unbundling, this work item proposes: - Specification of a standard interface, based on Diameter, for the DSP voice call proxy function to the ARP. - Specification of a DSP [...]. WID Approval Approved Y
15 - - - - - - - - - - -
15 SP-130416 New WID on Study on Need for multiple APNs (FS_MAPN) SA WG1 Objective: The objectives of this study are: - to provide details about the use cases where there is a need of control of APNs; - to identify potential new requirements to fulfil the use cases; - to identify po [...]. WID Approval Approved Y
15 SP-130417 New WID on Study on Co-ordinated P-GW change for SIPTO (FS_CSIPTO) SA WG1 Objective: The objective is to study use cases and identify potential requirements for network consideration of a) end-user experience and preferences and b) UE's knowledge of ongoing IP flow types ; regardi [...]. WID Approval Approved Y
15 SP-130418 New WID on Study on Enhancements for infrastructure based data communication between devices (FS_eICBD) SA WG1 Objective: The objective of this study item is to study: - Potential enhancements to support secure discovery of UEs of interest - Potential enhancements to support secure optimized end-to-end data communicati [...]. WID Approval Approved Y
15 SP-130399 New WID Study on Subscriber Privacy Impact in 3GPP (SPI) SA WG3 Objective: The SA WG3 objectives are as follows: - Identify and understand privacy related key issues impacting 3GPP network - Identify and potentially harmonize privacy requirements, e.g. MDT - Identify existi [...]. WID Approval Approved Y
15 SP-130357 New Study Item Description on 'HTML5 for a New Presentation Layer in 3GPP Services' (FS_HTM5) SA WG4 Objective: HTML5 is the new standard for the markup language for the web. HTML5 was revised to provide better support for advanced multimedia technologies while maintaining simple readability and improving comp [...]. WID Approval Approved Y
15 SP-130429 New WID Study on Lightweight Itf-N (FS_OAM_Itf-Nlight) SA WG5 Objective: This study item will: 1. Study on profile(s) for the Requirements for lightweight Itf-N. Based on the actual maintenance requirements of operators, select necessary requirements from currently defi [...]. WID Approval Noted Noted. It was decided to return this to SA WG5 to address the concerns raised and try to come to consensus on the scope of this work Y
15 SP-130430 New WID Enhancements of OAM aspects of Distributed MLB SON function SA WG5 Objective: The objective of the study is to - Identify whether D-SON MLB as currently standardized in 3GPP can be improved - In case potential areas of improvement are identified propose possible solutions The [...]. WID Approval Approved Y
16 - - - - - - - - - - -
16.1 - - - - - - - - - - -
16.1 SP-130359 3GPP Work Plan review at Plenary #61 MCC Work Plan Manager Presentation of 3GPP Work Plan review at Plenary #61 Work Plan Presentation Noted The MCC Work Plan Manager was thanked for this presentation, which was noted. Y
16.1 SP-130360 3GPP Releases Descriptions - Rel-11 to Rel-13 MCC Work Plan Manager 3GPP Releases Descriptions - R99 to Rel-13 http://www.3gpp.org/ftp/Information/WORK_PLAN/Description_Releases/ 3GPP Work Plan http://www.3gpp.org/ftp/Information/WORK_PLAN - Contains Release 1999 to Release [...]. OTHER Information Noted This was provided for information and was noted. Y
16.2 - - - - - - - - - - -
16.3 - - - - - - - - - - -
17 - - - - - - - - - - -
17.1 - - - - - - - - - - -
17.1 SP-130365 CRs to 21.801 on file formats and on the use of coloured fonts MCC Support Team Coordinator 21.801 CR0035R1; 21.801 CR0036; 21.801 CR0037 CR Pack Approval Approved Y
17.2 - - - - - - - - - - -
17.2 SP-130366 MCC Support Team Report MCC Support Team Coordinator MCC activities Status Report to TSG SA#61 Report Presentation Noted The MCC Support Team Coordinator was thanked for this presentation, which was noted. Y
18 - - - - - - - - - - -
18 SP-130488 Interleaved setup for 'one week TSG' TSG Chairs, Telefonica, Vodafone, NEC The present contribution suggests an alternative one-week-TSG setup using interleaving of TSG RAN and TSG SA for consideration. DISCUSSION Discussion Noted Noted. No change agreed until after 1-week TSGs trial Y

Created: 2013-09-12 06:43     END OF LIST

Last Allocated Document: SP-130506