3GPP active work programme
Click on UID to show list of all TSs and TRs associated with this work item.
Click on WI code to see a list of TSs and TRs specifically resulting from this work item.
Click on the percentage completion to see a list of approved Change Requests associated with this work item.
The "impact" shows an empirical best-guess of which TSs and TRs are likely to be modified as a result of the WI.
Work Items which have been abandoned are greyed out, and the TSG meeting at which they were abandoned is shown in the final column.
UID | code | title | release | lead body | completion | % done | WID TDoc | WID history | created date | last updated | remarks | abandoned |
---|---|---|---|---|---|---|---|---|---|---|---|---|
460013 | LTE_Relay | Relays for LTE | Rel-10 | C6, C4, S3, S2, R4, R2, R1 | 08/06/2011 | RP-110911 | history | 2009/11/30 | 14/02/2011 | RP#52 completed (open RAN4 Core & Perf parts moved to new Rel-11) | ||
460113 | LTE_Relay-Core | ... Core part: Relays for LTE | Rel-10 | R4, R2, R1 | 03/06/2011 | RP-110911 | history | 2009/11/30 | 14/06/2012 | RP#52 completed. Updated WID RP-101417=>RP-101911 (contains only Core part completed in Rel-10). Open RAN4 Core & Perf parts moved to new Rel-11 | ||
460213 | LTE_Relay-Perf | ... Deleted - Perf. part: Relays for LTE | Rel-10 | R4 | 03/06/2011 | RP-101417 | history | 2009/11/30 | 06/06/2011 | RP#52 stopped at 30% (no CRs so far) . Transferred completely to Rel-11 together with remaining core part | RP-52 | |
520020 | - | ... Stage 2 for Relays for LTE | Rel-10 | S2 | 08/06/2011 | history | 2011/06/06 | 06/06/2011 | SP#52 SP-110338 (S2-85/S2-112851) 23.401 Cat F CR#2128 Completion of Relay procedure overview | |||
500038 | LTE_Relay-Sec | ... LTE Relay Nodes Security | Rel-10 | C6, S3 | 22/03/2011 | SP-100733 | history | 2010/11/25 | 14/02/2011 | |||
500238 | - | ...... TR on LTE Relay Nodes Security | Rel-10 | S3 | 22/03/2011 | SP-100733 | history | 2010/11/25 | 14/02/2011 | SP#51 completed | ||
500138 | - | ...... Security for LTE Relay Nodes (Stage 2) | Rel-10 | S3 | 22/03/2011 | SP-100733 | history | 2010/11/25 | 14/02/2011 | SP#51 completed (impacting Stage 3 in CT and RAN) | ||
510011 | - | ...... CT6 aspects of LTE Relay Node Security | Rel-10 | C6 | 18/03/2011 | history | 2011/03/03 | 03/03/2011 | CP#51 completed | |||
510012 | LTE_Relay-CN | ... Core Network Impacts for Relay Nodes | Rel-10 | C4 | 18/03/2011 | CP-110094 | history | 2011/02/28 | 08/03/2011 | CP#51 completed |